BEFORE THE POLLUTION CONTROL HEARINGS BOARD
STATE OF WASHINGTON
|
WASHINGTON ENVIRONMENTAL COUNCIL, CENTER FOR ENVIRON- MENTAL LAW & POLICY, CONFEDERATED TRIBES OF THE COLVILLE RESERVATION, and ROGER LORENZ, Appellants, v. STATE OF WASHINGTON, DEPARTMENT OF ECOLOGY, and BATTLE MOUNTAIN GOLD COMPANY, Respondent. |
) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) |
PCHB NO. 97-146 PCHB NO. 97-182 PCHB NO. 97-183 PCHB NO. 97-186 PCHB NO. 99-019 FINAL FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER |
|
|
) |
|
This matter came before the board for hearing on May 11-20, 1998 and on September 14-17, 1999. The board was comprised of James A. Tupper, Jr., presiding, Ann Daley, and Robert V. Jensen. Gene Barker and Associates of Olympia, Washington provided Court reporting services.
For the 1998 hearing appearances were as follows:
Adam Berger for the Okanogan Highlands Alliance, the Washington Environmental Council, and the Center for Environmental Policy, Rachael Paschal for the Center for Environmental Law and Policy, Stephen H. Suagee for Confederated Tribes of the Colville Reservation, and Geraldine Payton for Roger Lorenz.
Assistant Attorney General Joan M. Marchioro and Assistant Attorney General Jay J. Manning for the Department of Ecology.
Glenn J. Amster, Michael J. Malmquist and Craig D. Galli for Battle Mountain Gold Company.
For the 1999 hearing appearances were as follows:
David Mann for the Okanogan Highlands Alliance and the Washington Environmental Council. Assistant Attorney General Joan M. Marchioro and Assistant Attorney General Tom McDonald for the Department of Ecology.
Glenn J. Amster, Michael J. Malmquist and Craig D. Galli for Battle Mountain Gold Company
FINDINGS OF FACT
Project
Description and Background
1. The Crown Jewel
Mine is proposed to be constructed near the summit of Buckhorn Mountain in
Okanogan County. Buckhorn Mountain is
located in the Kettle River Basin straddling the Myers Creek and Toroda Creek
watersheds. In 1991, the United States
Forest Service and Ecology entered into a partnership to complete a National
Environmental Policy Act (NEPA) and State Environmental Policy Act (SEPA)
environmental impact statement (EIS) for the proposed Crown Jewel Mine project.
2. The process
began with a series of scoping meetings in which the potential impacts of the
project were identified. At the
conclusion of project scoping in early 1992, Ecology received comments and
suggestions regarding possible alternatives to Battle Mountain Gold’s (BMG)
proposal. Staff from Ecology and the
Forest Service developed an array of alternatives for various mining and
milling processes and facilities. The
array of alternatives was drawn from reviews of relevant literature, the mining
experience of Ecology staff, and comments received during the scoping
process. Meetings were held throughout
1992 and 1993 to refine and accurately describe the alternatives
identified. The product of these
meetings is Chapter 2-Alternatives Including the Proposed Action of the EIS. The purpose of Chapter 2 was to describe the
proposed project and the identified alternatives to allow a meaningful
comparative analysis of all options and their respective environmental impacts.
3. During the time
the EIS was being developed, BMG applied to Ecology requesting water for the
proposed mine. On November 20, 1992,
BMG submitted 20 applications to Ecology’s Central Regional Office in
Yakima. BMG subsequently withdrew four
applications. In November 1994, BMG
published public notices for the remaining 16 applications. The applications requested six new water
rights, changes to eight existing water rights and two reservoir permits. Ecology received over 70 letters of protest
or concern regarding BMG’s applications.
4. Water supply is
limited in the Myers Creek and Toroda Creek basins. Myers Creek, which flows north into Canada where it meets the
Kettle River, was the subject of a general adjudication in the 1930s. In addition to the Washington surface water
users on Myers Creek, the adjudication included all of the Canadian users as
well. The most senior irrigation right
confirmed in the adjudication is a Class 2 right providing for diversion of
water just north of the Canadian border.
Ecology and its predecessor agencies have consistently honored requests
from Canadian authorities to regulate Washington users to protect this senior
right.
5. Toroda Creek,
unlike Myers Creek, historically has not been the subject of formal
regulation. Over the years, the
Washington State Department of Fish and Wildlife and its predecessor agencies
have stated to Ecology that the remaining unappropriated water of Toroda Creek
and its tributaries is required to maintain fish resources. While no formal closure is in place,
Ecology’s position has been that, absent augmentation with water from another
source, further appropriation of water in hydraulic continuity with Toroda
Creek during the months of July through September would be detrimental to
instream values in Toroda Creek and has denied applications for appropriation
on that basis.
6. In July 1994, as
part of the development of the EIS for the mine, an Instream Flow/Incremental
Method (IFIM) study was conducted on Myers Creek. The purpose of the study was to determine the instream flows
necessary for spawning and rearing of brook and rainbow trout. The IFIM study established the following
minimum flows for Myers Creek from February 1 through July 31: (1) minimum flow
in Myers Creek from February 1 to April 1 is 6 cubic feet per second (cfs); (2)
after April 1, when the 7-day running mean water temperature rises to 6ºC but
does not exceed 8ºC, the minimum flow is 9 cfs; and (3) once the 7-day running
mean water temperature rises above 8ºC, the minimum flow is 12 cfs.
7. Analysis of
BMG’s mine proposal through the EIS process and water rights investigation
indicates that the development of the mine and proposed appropriation of water
would result in streamflow depletions in the Myers Creek and Toroda Creek
basins. As the mine is developed,
groundwater will seep into the pit, and precipitation will collect in the pit
and fully lined Tailings Disposal Facility (TDF). Groundwater on Buckhorn Mountain is hydraulically connected to
tributaries of both Toroda Creek and Myers Creek. Likewise, precipitation in the vicinity of the TDF normally would
contribute to tributary flows. Absent
mitigation, therefore, groundwater and surface runoff captured by the pit and
TDF would cause a reduction in those flows.
Development of the mine also will cause a slight shift in the
groundwater divide on Buckhorn Mountain.
As a consequence, following the closure of the mine, a small amount of
water which previously flowed to the Myers Creek catchment will flow to the
Toroda Creek catchment. As part of the
reclamation of the mine site, BMG will pump water from the Starrem Creek
Reservoir to accelerate filling part of the pit with water. Upon completion of reclamation, and
establishment of a hydrologic equilibrium, the shift in the groundwater divide
will remain, causing predicted reductions of mean annual flow in Bolster and Gold
Creeks, respectively (Myers Creek catchment), and in Marias Creek (Toroda Creek
catchment), with corresponding increases in flows in Nicholson Creek. Because reduced flows in these drainages
might lead to impairment of senior rights and reduced flows necessary for fish
and instream resources, Ecology informed BMG that water was not available for
consumptive use in Myers Creek and Toroda Creek basins absent mitigation. In response, BMG developed a Streamflow Mitigation
Plan that is intended to compensate for the predicted impacts to streamflows
due to the mine.
8. The Streamflow
Mitigation Plan is designed to replace water in the affected basins in the
amounts of the predicted depletions during times of potential impairment. The Streamflow Mitigation Plan, which is
based on the hydrologic modeling performed for the EIS, provides mitigation
during the mine’s operation, reclamation and post-closure phases. During the operation and reclamation phases,
mitigation consists of pumping water from the Starrem Creek Reservoir, where
water diverted from Myers Creek and Starrem Creek will be stored, to the mine
head tank where it will be delivered through underground pipes to the affected
drainages. Water will be released to
all affected basins when IFIM flows are not being met in Myers Creek. Water will also be released to the Myers
Creek and Toroda Creek basins during typical low flow periods, regardless of
whether the IFIM minimum flow is being met in Myers Creek.
9.
After mining, all diversions of water will cease as the new water rights
will lapse and the changed certificates will revert to the prior permittees at
the previous point of diversion. The
remaining impact of the reclaimed mine will be the hydraulic shift between
Myers Creek and Toroda Creek drainages.
Post-closure mitigation to address the hydraulic shift consists of
drilling two nearly horizontal boreholes from the pit lake to Bolster and Gold
Creeks in the Myers Creek watershed.
The boreholes will contain HDPE plastic pipe with valves and flow meters
to regulate and measure flow rates.
Water will flow by gravity to the affected drainages throughout the year
in an amount equal to the total reduction in Myers Creek runoff caused by the
hydraulic shift.
10.
Pursuant to the Metals Mining and Milling Operation Act, ch 78.56 RCW,
BMG posted an Environmental Protection and Performance Security (EPPS) bond
with Ecology for the water rights the company sought. The purpose of this EPPS bond is to ensure BMG’s performance of
conditions placed upon any water right permits granted by Ecology. If BMG fails to comply with the specified
conditions, the bond provides financial resources for Ecology to carry out both
the short-term and long-term mitigation requirements envisioned in the
Streamflow Mitigation Plan.
Specifically, the bond provides funds for: (1) operation of the
streamflow mitigation system during the operation and reclamation phases of the
project; (2) construction of the boreholes and treatment system to deliver post
reclamation augmentation flows; (3) completion of an acceptable final
comprehensive Operations and Maintenance Manual for the mitigation plan; and
(4) establishment of the Myers Creek Charitable Trust to ensure the perpetual
operation and maintenance of the post reclamation mitigation system. The Trust will be created by BMG following
reclamation. BMG will fund the Trust
either directly or through the EPPS bond if BMG defaults on its obligations secured
by the bond.
11.
In the late spring of 1996, Phil Crane of Ecology’s Central Regional
Office was assigned to investigate the pending water right applications in the
Okanogan County portion of WRIA 60, including BMG’s 16 applications. Mr. Crane conducted the preliminary
investigation of BMG’s water right applications. In light of the large scale of BMG’s proposed project, the number
of water right decisions to be made, and the level of scrutiny being applied to
the project, Ecology decided that final decisions on BMG’s water right
applications would be made by the Program Manager for Water Resources. As Carol Fleskes had recently left that
position and no successor had been appointed, Ms. Fleskes was asked to make the
final determinations on BMGs pending applications.
12.
Ecology issued reports of examination granting 12 of the 16 applications
submitted by BMG:
Reservoir Permit Application No. R4-31558, the Starrem Creek Reservoir, requested a permit to store
water diverted under several water rights in the Myers Creek watershed. The reservoir would be located on Starrem
Creek, a tributary of Myers Creek. The
reservoir would be lined to reduce leakage, have a storage capacity of 428
acre-feet and would inundate 19.9 acres of land. The dam would be 59 feet high, with a crest length of 1300 feet
and crest width of 20 feet, and an estimated maximum depth of 49 feet. An eight-inch outflow pipe would deliver
water to the mine site. Ecology
approved the application, finding: (1) water is available for impoundment and
storage from changes to the existing water rights and new water rights
requested in Myers Creek basin; (2) existing water rights will not be impaired;
(3) the secondary uses at the mine for industrial mining, including dust
control and mitigation water, are beneficial uses; and (4) considering the
entire project, including the Streamflow Mitigation Plan, issuing the permit is
not contrary to the public interest.
Reservoir Permit Application No. R4-31741 requested a reservoir permit for the mine’s Tailings
Disposal Facility, which relies on two impoundment dams to contain the mine
tailings. DOE Ex. 9. The reservoir would be located near the
headwaters of Marias Creek, a tributary of Toroda Creek. Although designed to hold 360 acre-feet,
under normal operations of the mine the pool was projected to hold 10 to 20
acre-feet of water. A double liner
system and leak detection system would be installed to contain the tailings and
pond. Water in the reservoir would come
from the ore processing facility, mine pit, mine dewatering well, and, if
necessary for water quality reasons, the tailings underdrain. Water in the reservoir would be used at the
ore processing facility. Ecology
approved the application, finding: (1) water is available for impoundment and
storage from new water rights; (2) existing water rights will not be impaired;
(3) the secondary uses at the mine for industrial mining are beneficial uses;
and (4) considering the entire project, including the Streamflow Mitigation
Plan, issuing this permit is not contrary to the public interest.
Applications for change of Myers Creek
Adjudicated Certificate Nos. 45, 47, 48, 67, 68, 69, and 70, requested the right to use 0.16 cfs, 0.293 cfs, 0.187 cfs,
0.293 cfs, 0.093 cfs, 0.053 cfs, and 0.04 cfs, respectively, of water from
Myers Creek for irrigation of 94 acres.
The change applications sought to temporarily change the place of use
from the Leslie Ranch to the mine site, the point of diversion from its present
location to a point downstream on Myers Creek and the purpose of use from
irrigation to mining purposes. Because
the change applications proposed to transfer water out of the basin leaving no
opportunity for return flows, only the crop-water duty and consumptively used
water (evaporation) were considered for change. Ecology’s investigation determined that the historic beneficial
use of the seven adjudicated rights was the irrigation of approximately 48
acres and represented a total instantaneous quantity of water of 0.64 cfs. The 0.64 cfs authorized corresponded to
Certificate Nos. 45, 47 and 48. Ecology
found that the proposed change in point of diversion will not impair existing
rights, changing the place of use will not impair other water rights since only
the consumptively used water was considered for change, and the proposed change
in the purpose of use will not impair other water rights. Based on this information, Ecology granted
BMG’s applications to change Certificate Nos. 45, 47 and 28. Due to Ecology’s finding regarding the
historic beneficial use of the Leslie Ranch adjudicated certificates, BMG’s applications
to change Certificate Nos. 67, 68, 69 and 70 were denied.
Application for Change of Ground Water
Certificate No. G4-22893C, requested a
change to a certificated right to use 400 gallons per minute (gpm) of water
from a well for irrigation of 120 acres.
DOE Ex. 17. The application
sought a temporary change in use from irrigation to mining and place of use
from its present location to the mine site.
Pump tests performed by BMG indicated that the well produced less than
the 200 gpm authorized under the certificate.
Because the water under the proposed change would be transferred out of
the basin leaving no opportunity for return flows, only the crop water duty and
consumptively used water (evaporation) were considered to change; resulting in
a maximum annual quantity authorized for change of 113.88 acre-feet per year
during the irrigation season. Ecology
determined that the proposed change in the place of use will not impair other
water rights because only the consumptively used water was considered for
change and changing the purpose of use will not impair other existing water
rights. Based on these findings,
Ecology approved BMG’s change application authorizing a maximum instantaneous
withdrawal of 265 gpm and a maximum annual quantity of 113.88 acre-feet per
year from April 1 through October 1.
Ground Water Application No. G4-31611 requested a water right for use of 400 gpm, up to 240
acre-feet per year, of ground water from the mine pit for general mining
purposes. DOE Ex. 2. Because excavation of the mine pit would
result in a small shift in the hydraulic divide between Myers Creek and Toroda
Creek basins, the Streamflow Mitigation Plan provides for the distribution of
water in perpetuity to Gold and Bolster Creek within the Myers Creek basin to
compensate for the shift in the divide.
Ecology approved the application, finding: (1) water is available from
the Toroda Creek drainage provided that adequate water is delivered to the
affected drainages as described in the Streamflow Mitigation Plan; (3) the
proposed use is beneficial; and (4) considering the entire project, including
the Streamflow Mitigation Plan, issuing the permit is not contrary to the
public interest.
Ground Water Application No. G4-31612 requested 100 gpm of water from an underdrain emerging from
below the tailings facility. DOE Ex.
3. The underdrain would be composed of
several gravel-filled trenches designed to draw water from under the tailings
facility to a collection pond where the water would be sampled for water quality
purposes. Water would be appropriated
under the permit only if the water emanating from the underdrain exceeded
Washington’s water quality standards.
If water were appropriated, it would be pumped into the tailings
facility for use at the mill and ore processing facility. Ecology approved the application, finding:
(1) without augmentation with water from another source, water is not available
from the Toroda Creek drainage during the months of July through September and
whenever water is withdrawn from the infiltration trench, an equal amount of
water must be delivered to the drainage just downstream from the point of
withdrawal; (2) other water rights should not be impaired as long as the
augmentation for this permit is carried out as described; (3) the proposed use
is beneficial; and (4) considering the entire project including, the Streamflow
Mitigation Plan, issuing the permit is not contrary to the public
interest.
Ground Water Application No. G4-31272 requested 15 gpm of water from a well for domestic supply
for the mine site. DOE Ex. 4. Water would be used for toilets, showers and
drinking supply. The annual water usage
was estimated at 7.5 acre-feet. Ecology
approved the application, finding: (1) water is available from Toroda Creek
drainage provided adequate water is delivered to the affected drainages as
described in the Streamflow Mitigation Plan; (2) other water rights should not
be impaired as long as the augmentation and mitigation proposed for the project
is carried out according the Streamflow Mitigation Plan; (3) the proposed use
is beneficial; and (4) considering the entire project including, the Streamflow
Mitigation Plan, issuing the permit is not contrary to the public interest.
Ground Water Application No. G4-31556 requested up to 50 gpm from a well to assist in dewatering
the mine pit. DOE Ex. 5. The water withdrawn would be used as process
water at the mine site. Ecology approved the application, finding: (1) water is
available from Toroda Creek drainage provided adequate water is delivered to
the affected drainages as described in the Streamflow Mitigation Plan; (2)
other water rights should not be impaired as long as the augmentation and
mitigation proposed for the project is carried out according the Streamflow
Mitigation Plan; (3) the proposed use is beneficial; and (4) considering the
entire project including, the Streamflow Mitigation Plan, issuing the permit is
not contrary to the public interest.
Surface Water Application No. S4-31554 requested 5 cfs of water from Myers Creek, up to 650
acre-feet per year. DOE Ex. 6. Diversion of water under the permit would
occur during the spring freshet and high runoff period between February 1 and
July 31. Water would be diverted from
Myers Creek to the Starrem Creek Reservoir and ultimately pumped to the mine
site for use in mining operations.
Ecology approved the application, finding: (1) water is available from Myers Creek during the spring freshet,
provided minimum instream flows as established by the IFIM study are met; (2) provided
the Streamflow Mitigation Plan is implemented, the proposed appropriation will
not impair existing water rights; (3) the proposed use is beneficial; and (4)
considering the entire project, including the Streamflow Mitigation Plan,
issuing the permit is not contrary to the public interest.
Surface Water Application No. S4-31555 requested 20 cfs from Starrem Creek, a tributary of Myers
Creek. DOE Ex. 7. A dam would be constructed near the mouth of
this watershed and would impound the waters of Starrem Creek. The water would be used for industrial
mining, including milling, ore processing, dust suppression, fire control,
reclamation and streamflow augmentation.
The diversion would appropriate water during the spring freshet and high
runoff period between February 1 and July 31.
Water would be stored in Starrem Creek Reservoir for later use at the
mine site. Ecology approved the
application, finding: (1) water is available from Starrem Creek during the
spring freshet provided minimum instream flows on Myers Creek are met; (2)
provided the Streamflow Mitigation Plan is implemented, the proposed
appropriation will not impair existing water right; (3) the proposed use is
beneficial; and (4) considering the entire project, including the Streamflow
Mitigation Plan, issuing the permit is not contrary to the public interest.
13. On November 3,
1997, Ecology issued its decisions on BMG’s applications. Notice was sent to BMG, all protestants and
interested parties. Appellants timely
appealed Ecology’s decisions to the Board.
Pit Inflow
Study/Stream Depletion - Technical Issues
14. The pit inflow
study, stream depletion report, and mitigation plan all suffer from serious
omissions and flaws in methodology. The
original mitigation plan underestimated the magnitude of the streamflow
depletions and required mitigation quantities.
Just prior to the original hearing BMG and its consultants substantially
increased their streamflow depletion and mitigation estimates. These revised values still fall far short of
accurately predicting depletions and required mitigation. The mitigation plan is unprecedented in its
complexity and required permanent duration.
The last minute revisions demonstrate substantial uncertainty in the
hydrogeologic modeling and streamflow depletion estimates underlying the
mitigation plan. The uncertainty and
errors, coupled with the extremely water-short status of the Myers and Toroda
Creek basins, make it unreasonable to conclude that the mitigation plan will
prevent impairment to existing rights, instream values, and the public
interest.
15. The Roosevelt
adit is an abandoned underground mine located on the eastside of Buckhorn
Mountain. Excavation of the Crown Jewel
pit will reduce the amount of groundwater that collects in the adit and
discharges into Nicholson Creek. The
streamflow depletion study failed to consider how reduced flows from the
Roosevelt adit will affect streamflow reductions in Nicholson Creek. The failure to incorporate flow depletions
in the Roosevelt adit caused the stream flow depletion report to underestimate
depletions in Nicholson and Toroda Creeks.
BMG concedes that the original calculations underestimated
depletions. It is not clear whether the
revised depletion estimates are still too low.
16. The stream
depletion study and mitigation plan focus exclusively on how the capture of
groundwater discharge and surface runoff by the mine pit would reduce flows in
adjacent creeks. However, the
mitigation plan failed to account for flow reductions in Marias Creek caused by
the capture of precipitation within the lined tailings pond. BMG concedes that the original mitigation
plan entirely overlooked this impact and increased its estimate of streamflow
reductions and required mitigation. It
is unclear whether the revisions still underestimate expected depletions.
17. The stream
depletion study relies on precipitation data and streamflow measurements from
the 1993 and 1994 water years to establish linear relationships between
precipitation and streamflow for monitoring sites on affected streams. These linear relationships were then used to
estimate baseflow, surface runoff, and streamflow depletions at these sites in
an average precipitation year.
Appellants criticized the use of estimated rather than actual mine site
precipitation data for water year 1993 on the grounds that the methods used to
estimate 1993 data were unreliable and created significant uncertainty in
estimates of streamflow depletions. In
response to this critique, the precipitation analysis underlying the streamflow
depletion estimates was recalculated.
The new analysis, which incorporates an additional three years of actual
mine site precipitation data, results in very different precipitation
estimates. This raises a substantial
concern that the use of such limited precipitation data results in highly
uncertain depletion estimates. The use
of an additional three years of precipitation data in the revised analysis does
little to reduce the uncertainty inherent in relying on limited data.
18.
The stream depletion report and the mitigation plan predicted that
post-reclamation overflow from the refilled pit lake would increase flows to
Nicholson and Toroda Creeks over pre-mining conditions. However, this analysis failed to take into
account revegetation of the pit lake area, as described in the EIS. Revegetation will decrease surface runoff
and increase losses due to evapotranspiration, thereby reducing pit
inflows. Accounting for revegation and
increased evaporation from the pit lake surface, there will be a net
consumption of water by the pit lake during dry years, particularly in summer
months when demand is highest and water is most scarce. Instead of increased flow in Nicholson Creek
post-reclamation, there will be unmitigated reductions in flow during the most
critical periods of need.
Further, because post-reclamation
mitigation is required in perpetuity to offset the permanent shift in the
groundwater divide, the boreholes and treatment facilities required for
post-reclamation mitigation must be maintained forever.
19. Accurate
calculation of baseflow and surface runoff in the affected streams is critical
to an estimate of streamflow depletion.
The higher the measured flows, the greater the estimated impact from
loss of catchment area to the mine pit.
BMG measured flows in affected streams using both weir or culvert
measurements and concurrent bucket measurements. The bucket measurements were consistently and significantly
higher than weir or culvert measurements; in fact, bucket measurements were 67%
to 92% higher. In calculating baseflow
in the stream depletion report, the report relied exclusively on the lower weir
and culvert measurements and completely disregarded the higher bucket measurements. Use of the bucket measurements would have
increased stream depletion estimates by 28.4 to 39.0 AF/year.
20.
Accurate hydrogeological characterization of the area surrounding the
pit is essential to accurate analysis of estimated streamflow depletions. Inaccurate or uncertain hydrogeologic
characterization creates uncertainties in computer modeling used to predict the
area of groundwater recharge captured by the pit. Uncertainties in modeling the pit capture zone translate directly
in uncertainties in predicted streamflow depletions.
Reliable field testing of aquifer
properties has been limited largely to the north-central area of the pit itself
and is scarce in areas outside the pit where streamflow depletions will
actually occur. The tested areas
revealed the existence of preferential flow conduits and other heterogeneous
hydraulic features that significantly affect groundwater flow patterns near the
top of Buckhorn Mountain. These
findings are consistent with the fractured bedrock structure of the area’s
hydrogeology.
Nonetheless, the model originally
used to predict the size and shape of the pit’s capture zone assumed that the
untested portions of the aquifer behave like an equivalent porous media with no
preferential flow features that would affect the extent of the capture zone and
correspondent streamflow depletions.
The likelihood that untested areas within the pit’s zone of influence
contain such heterogeneities was not considered in the original computer
modeling, nor was the possibility that preferential flow conduits in the
characterized portion of the pit had been inaccurately modeled.
Mitigation Plan -
Technical Issues
21. The mitigation
plan fails to account for all streamflow depletion attributable to the mine pit
while the pit is filling with water during the reclamation phase. As the fully excavated pit is filled with
water, adjacent groundwater storage will gradually be replenished, but that
replenishment of this storage lags behind the refilling of the pit. The streamflow depletion analysis does not
reflect any lag time, but rather simply models the final steady state after pit
filling is completed. This omission
results in an underestimation of the extent of streamflow depletion during pit
filling.
22. The mitigation
plan also fails to consider or account for lag time between release of
mitigation water from the discharge points and its appearance in affected
streams. The Streamflow Mitigation Plan Evaluation published in March 1998
states that the lag time will be from 1.5 months to just over two years between
release of mitigation water and its appearance in the intended stream. Recalculations of the lag time in pre-filed
written testimony submitted on behalf of respondents reduced the lag time to a
matter of days. The revised
calculations are derived from assumptions of soil conductivity values that are
significantly higher than the values actually documented in the EIS from
testing of deposits on site. As a
result, the board accords these recalculations no weight.
23.
The mitigation plan also fails to adequately address depletion of Ethel
Creek in the Myers Creek drainage. The
mitigation plan incorrectly assumes that there would be no streamflow depletion
to Ethel Creek. In fact, the pit zone
of influence will extend into the Ethel Creek watershed and cause a depletion
for which no mitigation is provided either during mining, reclamation or
post-reclamation on a permanent basis.
Respondents modeling found that there is in fact a reduction in Ethel
Creek flows of 2 gallons per minute or 0.3 acre feet per year.
24.
Ecology failed to consider the cumulative impacts of granting BMG’s
water rights on local water supply in light of concurrently planned or
reasonably foreseeable future actions.
For example, Ecology did not consider how granting BMG 1,528.5 AF/year
in new withdrawals would affect the ability of local water supplies to
accommodate anticipated increases in population growth or what the cumulative
impacts of the mine and growth would be.
The EIS predicts a substantial 14% population increase locally over the
next ten years regardless of whether the mine is developed. Mine operations would add another 2% in
local population growth. The EIS states
that housing development in all incorporated communities within the study area
has been “problematic” due in part to water supply constraints, and the
“[a]vailability of water is a particular concern.” The EIS acknowledges that it will be particularly difficult to
meet future local water demand because most of the new housing development will
likely occur beyond the reach of existing public water supply systems.
Ecology never evaluated whether the
local water supply is sufficient to support anticipated population growth in
light of increased demand from BMG’s diversions. Furthermore, Ecology never considered the cumulative impacts of
BMG’s new rights and existing and future demand from exempt wells and
reasonably foreseeable development projects, either independent of or prompted
by the mine’s development.
25.
Ecology failed to consider the impacts of new withdrawals in Myers and
Toroda Creeks on flows in the Kettle River.
Both Ecology and BMG were aware that state wildlife agencies had
established recommended minimum flows in the Kettle River to protect aquatic
resources. Ecology has conditioned other
water rights granted in Kettle River tributaries on maintenance of these
minimum flow levels. Ecology’s failure to consider the potential adverse
impacts of new withdrawals on Kettle River flows in its decision to grant BMG’s
applications is inconsistent with past actions and problematic for this
application.
26.
In summary, the streamflow depletion report and mitigation plan suffer
from a number of deficiencies. Taken
together, the deficiencies in pit inflow study, the streamflow depletion report
and mitigation plan, compel the conclusion that the mitigation plan contains
too much uncertainty to adequately protect existing rights and instream flows
from harm. The level of uncertainty is
demonstrated by the prehearing revisions to these studies. Even as revised, the mitigation plan
substantially underestimates the likely streamflow depletions and required
mitigation quantities. The mitigation
plan does not protect existing rights and instream flows because it is too
speculative and error-ridden to compensate for streamflow depletions likely to
be caused by excavation of the mine pit.
Quantity of Water
Rights Available for Transfer
27. Appellants
contend that Ecology improperly calculated the extent of beneficial use for the
proposed transfer of the Lost Creek and Leslie Ranch rights. To quantify the Lost Creek well right,
Ecology relied on affidavits attesting to 120 acres of irrigation and
disregarded aerial photographs showing only 97.9 acres under irrigation. To quantify the Leslie Ranch rights, Ecology
relied on aerial photographs showing 48 acres of irrigation and disregarded an
affidavit stating that only 46 acres had been irrigated historically and that
19 of those acres had not been irrigated since 1989. The evaluation by Ecology was reasonable under the circumstances
and based on the available evidence.
There is no indication that Ecology simply quantified the rights by
relying on whatever evidence showed the highest historic use, rather than the
average of recent, continuous use. The
estimates of beneficial use did not result in any expansion of the transferred
rights
401 Certification
28.
We turn now to the § 401 Certification for the Crown Jewel Mine Project
issued by Ecology on January 13, 1999.
The Certification was issued in connection with BMG’s application for a
dredge and fill permit from U.S. Army Corps of Engineers (Corps) under Section
404 of the Federal Clean Water Act. The
Corps issued BMG a § 404 Permit, accompanied by a Record of Decision, on June
28, 1999 (Department of the Army Permit No. 199-2-4-1078 and Record of
Decision). The § 404 Permit
incorporates and requires BMG to comply with the conditions contained in
Ecology’s § 401 Certification.
29. Issuance of the
§ 401 Certification and the § 404 Permit culminated a process that began with
initial proposal of the Crown Jewel Mine Project and continued through the
development of the EIS. The Corps
became a formal “cooperating” agency in the EIS preparation process in late
1992. In addition to wetlands issues,
Ecology was also closely involved in overseeing the geochemical testing, waste
rock characterization, pit lake modeling and assessment of waste rock impacts
done as part of EIS preparation.
30.
The Project area contains just under 50 acres of wetlands. Under the initial and several subsequent
revisions of BMG’s Mine Plan, the tailings and waste rock disposal facilities
would have covered over 10 acres of these wetlands, including the “frog pond”
wetland located southwest of the north waste rock disposal site and the
“nine-acre” wetland near the head of the Nicholson Creek drainage. These two wetlands were subsequently
determined by the agencies to be the most valuable wetlands on the site.
31.
The proposed mine plan was revised during the EIS process to reduce
direct wetland impacts by 2/3, to approximately 3.5 acres. The revised configuration avoided impacts to
the frog pond and the nine-acre wetland.
In March, 1996, following release of
the draft EIS, BMG formally submitted a joint application for a § 401 Certification
and a § 404 Permit. The agencies
determined at that time that notice of the application would not be issued
until the EIS was finalized.
The final EIS was issued on January
1997. It included a description of
aquatic resources impacts and of mitigation measures then proposed by BMG and
being considered by the agencies. The
EIS also included a discussion of the pit lake water quality modeling and
results, and based on those results, required
BMG to prepare a Contingent Pit Water Treatment Plan, to be secured by a
performance security. Both a detailed
description of the geochemical testing program performed by BMG and the
agencies to characterize waste rock, pit wall rock, ore and tailings at the
site, and an assessment of the water quality impacts and risks presented by
such materials to surface and groundwater were also included.
In addition, the EIS noted that BMG
would be required to secure Ecology and Department of Natural Resources (DNR)
approval of a waste rock management plan, to address potential acid generation
and metals release, as part of the National Pollutant Discharge Elimination
System (NPDES) and state Waste Discharge permit process and prior to placement
of waste rock.
Notice of the BMG’s § 401 and § 404
applications was published and a public hearing was held in June 1997. BMG began working with Ecology to develop
the Contingent Pit Water Treatment Plan as required by the EIS, which together
with a companion pit water monitoring plan was submitted in final form to
Ecology in May of 1998.
Also in May 1998, BMG withdrew and
then resubmitted its § 401 application because the one-year time period for
Ecology’s certification decision was about to lapse. Notice of the resubmitted application was published on June 19,
1998, and public comments were accepted until July 30, 1998. The notice expressly referenced BMG’s
proposed contingent pit water treatment and monitoring plans, and sought
comments on the same.
In December 1998, Ecology issued a
SEPA Addendum describing enhancements which had been made in BMG’s Aquatic
Resources Mitigation Plan and Streamflow Mitigation Plan since issuance of the
EIS, and describing the Contingent Pit Water Treatment Plan. The enhancements included doubling of the
size of the Myers Creek wetlands mitigation site, from 50 to 97 acres;
supplying augmentation water to the nine-acre wetland and another wetland
denominated “C-9” to protect both from potential flow reductions; providing
additional mitigation at the Pine Chee, Bear Trap Canyon and Cedar Grazing
Allotment sites; and creating additional seeps, springs and wetland areas at
the site on Buckhorn Mountain.
In the Addendum, Ecology concluded
that the primary effect of the various additional mitigation and contingent
mitigation measures was to further reduce environmental impacts, and that while
the modifications and additions would themselves cause some impacts, no
additional significant adverse impacts beyond those identified in the original
environmental document have been identified.
The United States Forest Service and the Bureau of Land Management, who
manage most of the land at the site, provided their comments on the Addendum
and concurred with the conclusion of no significant impacts.
32. About a month
after release of the Addendum, on January 13, 1999, Ecology issued BMG its §
401 Certification. The § 401
Certification relies substantially on the NPDES permit process. During the time Ecology was preparing the
EIS and processing BMG’s § 401 Certification, it was also processing BMG’s
other water quality permits. On
September 19, 1997, Ecology approved BMG’s Construction Stormwater NPDES
permit, authorizing discharges associated with construction of the mine and all
ancillary facilities, other than discharges from waste rock disposal
facilities, which require issuance of the pending individual NDPES/Waste
Discharge Permit. This Construction
Stormwater Permit was appealed by OHA to the Board, which ultimately rejected
the appeal and upheld the Permit.
Compliance with Construction Stormwater Permit is a condition of the §
401 Certification.
The individual NPDES/Waste Discharge
permitting process formally began in April 1996, when BMG submitted a permit
application to Ecology. By November
1997, Ecology issued a draft permit and fact sheet that included design
requirements, treatment requirements, monitoring effluent limits and
performance security.
After receipt of the draft permit,
BMG proposed alternative points of compliance (APOC), one for the north waste
rock facility and one for the south waste rock facility, for certain
constituents that could infiltrate into groundwater from beneath the facilities
and could potentially exceed groundwater enforcement limits at the toe of the
facilities. Ecology has discretionary
authority to approve an APOC under WAC 173-200-060.
BMG prepared and submitted two
reports in support of its application for the APOC. One of the reports is titled Evaluation
of Groundwater Quality Beneath the Waste Rock Disposal Areas (BMG Feb. 1999)(Groundwater
Evaluation). The Groundwater Evaluation
contains predictions of groundwater quality at two locations for each of the
two proposed waste rock disposal facilities in an assumed groundwater well located
at the ultimate toe of each of the waste rock disposal facilities, and at a
proposed APOC well located downhill from each of the waste rock disposal
facilities.
The Groundwater Evaluation’s
prediction of metal concentrations is derived from a steady state thermodynamic
model developed for the proposed waste rock facilities. The Groundwater Evaluation’s prediction of
nitrate concentrations, and also a confirmatory prediction of metals
concentrations, are derived from a transient mixing cell model (Mixing Cell
Model).
The results predicted by the two
Models, as documented in the Groundwater Evaluation, are that nitrate and
certain metals would exceed groundwater limits directly at the waste rock
facility toe wells, but that all constituents would meet all groundwater
standards at the proposed APOC wells.
Ecology has not yet finally approved the Groundwater Evaluation, nor has
it approved the APOC. Both are part of
the NPDES/Waste Discharge process.
In light of the prediction in the
Groundwater Evaluation that groundwater underneath and at the toe of the waste
rock facilities could exceed groundwater standards, and concerns by Ecology
that some of this groundwater could potentially discharge to down gradient
surface water features, Ecology required BMG to develop a monitoring plan designed
specifically to protect these features.
The plan, referred to as the Technical
Memorandum, North and South Waste Rock Facility hydrologic Monitoring Plan
(‘Technical Memorandum”) was developed by BMG under the guidance of Mr. Bob
Raforth of Ecology, and imposed as a condition of the
§ 401
Certification.
The Technical Memorandum includes
installation of six additional groundwater monitoring wells, located between
the waste rock facilities and the frog pond (2 wells), wetland C-9 (1 well),
and wetlands C-6, C-7, and Spring JJ-15 and Seep JJ-34 (3 wells). The plan also requires regular surface water
quality monitoring of these features.
33.
In addition to the Groundwater Evaluation (an earlier version) and the
Technical Memorandum, when Ecology issued the § 401 Certification, it had
reviewed and was familiar with at least the following NPDES-related water
quality reports submitted by BMG and related to waste rock water quality:
AKART Analysis, Waste
Rock Disposal Areas, Crown Jewel Project (Arcadis Geraghty & Miller,
April 1998);
Water Quality
Prediction, Crown Jewel Project (Montgomery
Watson, October 1998);
Waste Rock
Management Plan, Crown Jewel Project (Montgomery
Watson, October 1998) (“Waste Rock Management Plan”);
Conceptual Design
Report Diversion Channels and Sediment Traps
(Golder & Associates); and
Hydrologic
Monitoring Plan, Crown Jewel Project
(Montgomery Watson, Sept. 1998).
34. Based on this
review Ecology concluded that there is reasonable assurance that the Crown
Jewel Project will comply with water quality standards, and that waste rock
discharges can be controlled through an NPDES/Waste Discharge Permit. Based on this conclusion Ecology issued the
§ 401 Certification.
35.
The proposed Crown Jewel Mine will result in the creation of an open pit
of approximately 116 acres on the top of Buckhorn Mountain. This pit will be approximately 800 feet deep
and extend 350 feet below the existing water table. During mining, a series of wells and pumps will ensure that
groundwater and surface water do not seep into and accumulate in the pit. At the conclusion of mining, the former pit
will begin to fill with water and create a lake in the northern portion. Water from the Starrem Creek reservoir will
be pumped into the pit lake until it is filled to approximately the 4,850-foot
level. This enhanced filling proposal
is expected to take five years. The
filled lake will be approximately 350 feet deep and have steep side slopes.
36. The Certification sets forth a determination by Ecology that the pit lake will be a water of the state under RCW 90.48.020 and subject to state water quality standards. The proposed pit lake will also discharge to surface waters. Once the pit lake is filled, it will discharge into Nicholson Creek. The discharge to Nicholson Creek will be controlled through an engineered outlet. The Nicholson Creek discharge is necessary for downstream water rights as well as for mitigation in Wetlands C1 and potentially the Frog Pond. Additionally, pit water will be discharged from the pit lake into both Gold and South Bolster Creek through subsurface bore holes. This water is necessary for mitigation of downstream water rights and beneficial uses. It is also predicted that approximately 6.6 acre feet per year (or 4.1 gallons per minute) will be lost from the pit lake to groundwater seepage. This seepage is expected to reach surface waters approximately 1,500 feet from the pit in the Gold Bowl drainage. There also exists the likelihood for large-scale preferential flow features on Buckhorn Mountain that would introduce more uncertainty for prediction of groundwater flow patterns and rates. A preferential flow feature crossing the filled pit lake would likely cause significant unanticipated seepage loss.
37.
Consequently, in addition to being a water of the state itself, the
water in the filled pit lake will discharge to surface waters through seepage
and through engineered output. Much of
the water released through engineered outputs is necessary for mitigation of
either aquatic resources or downstream water rights or beneficial uses.
38.
The pit lake is projected to exceed applicable water quality
standards. The § 401 Certification
states:
The FEIS
for the project includes a prediction that water in the filled pit lake will
exceed the Washington State Freshwater Chronic and Acute Criteria for one or
more toxic water pollutants.
This
prediction is based on modeling prepared by Schafer & Associates in 1995
and 1996. The modeling results are
produced in the Final Environmental Impact Statement at § 4.6.3; Table 4.7.4;
and Appendix E. Notwithstanding these
water quality predictions, the Department of Ecology cites two reasons for its
ability to provide reasonable assurance that water quality in the pit lake will
not exceed standards. First, Ecology
believes that the prediction is conservative.
Second, even if standards are exceeded, Ecology believes that water in
the pit can be treated.
39. The geochemical
modeling prepared for the pit lake is not, in fact, conservative in
nature. The pit lake water quality
modeling relied on what are called humidity cell tests (HCT) that were
conducted over a shortened timeframe and on an inadequate number of samples. Leachate concentrations from week 15 HCT
results form the foundation for prediction of metal concentrations in the pit
lake. The short length of the tests
makes it extremely unlikely that maximum metal concentrations were attained
from the tests. Metal concentrations
and pH values used as inputs to the model did not always reflect the highest
metal concentrations or the lowest pH values observed in the HCTs. In addition, leachate metal concentrations
for week 15 of the tests appear to be invalid due to exceedence of holding
times and undocumented storage and preservation methods. For these reasons, the board does not
consider the predicted concentrations for the pit lake to be environmentally
conservative. After initial filling
with storm reservoir water, when concentrations will be relatively low, pit
lake water quality is expected to degrade and contain concentrations of toxic
metals that will exceed state water quality standards.
40.
The Certification responds to the eventual contamination in the pit lake
by requiring the construction of a water treatment plant. The timing of plant construction will be
triggered by water quality monitoring during reclamation. If the monitoring results confirm
contamination, BMG will be required to proceed with implementing the Contingent
Pit Water Treatment Plan. The plan
calls for the construction of a water treatment facility that will require
perpetual maintenance and upkeep. The
plan does not require any assurance for meeting water quality standards during
the seven and a half years it will take to construct and implement a treatment
plan. During this time contaminated
water will be discharging from the pit lake to surface and ground water.
Waste Rock
41.
As discussed above, the proposed mine project will result in the
creation of two large waste rock facilities.
The North Waste Rock pile is proposed to hold approximately 53 million
tons of rock and cover roughly 161 acres.
The North Waste Rock pile is proposed in the headwaters of Nicholson
Creek. The South Waste Rock pile is
proposed to hold over 39 million tons or rock and cover approximately 127
acres. Groundwater flow from the South
Waste Rock pile will likely reach Marias Creek.
42.
The § 401 Certification recognizes that there are significant issues
remaining regarding leachate from the waste rock:
The project will result in discharges of leachate from two
areas of waste rock to groundwater.
These discharges are predicted to exceed the state’s groundwater
standards for several contaminants. The
applicant has provided a report showing that all known, available and
reasonable methods of prevention, control, and treatment (AKART) will not be
adequate for these discharges to meet the state’s groundwater standards at the
toe of the waste rock piles. The
applicant has therefore requested alternate points of compliance for the
leachate to meet groundwater standards.
Ecology has not yet approved the request.
For the North Waste Rock pile, the applicant has requested
an alternate point of compliance to be located approximately at Sediment Trap
6. There are two aquatic resources
identified between the North Waste Rock pile and this requested point of
compliance-the Frog Pond and Wetland C9.
For the South Waste Rock pile, the applicant has requested an alternate
point of compliance to be located just down gradient from the tailings
facility. There are several aquatic
resources between the South Waste Rock pile and this requested point of
compliance, including Wetlands C6 and C7, Spring JJ15, and Seep JJ34. Some of the predicted contaminants in the
leachate may also exceed surface water quality standards and acute or chronic
criteria as well as exceed the groundwater standards.
§ 401
Certification, pp. 12-13. The basis for
the § 401 Certification’s determination that leachate will exceed groundwater
standards are a series of reports provided by Battle Mountain Gold to the
Department of Ecology.
43.
It is probable that the existing geochemical modeling for the waste rock
under-predicts
the contaminant level in the waste rock leachate. The use of metal concentrations from flawed test results and the
use of low metal concentrations from humidity cell leachate tests has resulted
in a potentially unreliable underestimation of metal concentrations in leachate
used for the waste rock model.
44. Knowledge of discharges
from the proposed waste rock facilities is limited. At present, we know that the leachate that will discharge from
the waste rock piles is predicted to violate state groundwater standards and
that this leachate will travel down gradient as groundwater and discharge to
surface waters. Ecology has not
accepted Battle Mountain Gold’s predicted flow model describing the path or
speed that the leachate will follow from the waste rock facility to surface
waters. We note that during the first
phase of the hearing in 1998 the respondents represented that mitigation water
will flow rapidly through the system to receiving waters. In the second phase of the hearing
respondents operated on the opposite assumption that contaminated groundwater
from the waste rock piles will take years to reach surface waters. Ecology has not conducted its own modeling
to make its own determination on this important issue. Ecology also has not accepted Battle
Mountain Gold’s prediction of water quality down gradient of the waste rock
piles. Neither has Ecology conducted
its own model of water quality down gradient from the proposed rock piles. In short, Ecology’s review of discharges
from the waste rock facilities is a work in progress. Ecology’s determination that it could provide reasonable
assurance is based on its belief that it can control discharges through the
NPDES permit process.
45. The fate and
direction of waste rock leachate is a significant area of concern. Where the contaminated leachate will go
raises two significant areas of concern: contamination of Nicholson or Marias
Creeks as well as the Frog Pond located immediately adjacent to the North Waste
Rock Facility.
46. Hydrogeologic
characterization in the vicinities of the proposed waste rock facilities is
largely limited to definition of surface features. Additional characterization is required before monitoring systems
can be designed and assurances provided.
Characterizations performed within the proposed pit area cannot be
reasonably extrapolated to surrounding areas, especially at the level of detail
needed to predict contaminant transport pathways. However, evidence from the pit area and the surrounding areas
supports the presence of large-scale heterogeneities and preferential flow
features. Such features can have a
profound influence on groundwater flow patterns and contaminant transport.
47. Model
predictions of groundwater flow directions surrounding the proposed facilities
are also insufficient to establish that a monitoring system based largely on
modeled predictions can provide reasonable assurance that contaminants would be
detected before reaching surface water.
The model largely assumes a homogeneous bedrock aquifer outside of the
proposed pit, thus disregarding the influence of potential heterogeneities and
preferential flow features.
48. Prediction of
flow and transport is typically much more difficult in fractured rock than in
porous media. Heterogeneities that
assert a relatively small influence on regional groundwater flow can strongly
influence patterns of transport. A
relatively large portion of contaminants can be transported in relatively few
features, and prediction of mixing along a groundwater flow path is less
certain than for more homogeneous porous media. An isotrophy in bedrock aquifers (due to fractured geometries)
can cause contaminants to move in directions inconsistent with predictions
based on groundwater level monitoring.
These additional uncertainties dictate increased conservation in both
monitoring and predictive analyses.
49. The
effectiveness of groundwater modeling systems for detecting subsurface
contamination can be significantly reduced due to inherent uncertainties and
heterogeneities. These features also
make treatment of contamination in fractured rock more difficult and typically
less successful.
50.
There are no firm conclusions on the range of predictions for the length
of time it would take for groundwater moving from the North Waste Rock pile to
reach the Frog Pond. Predictions range
from days to decades. While a
monitoring well next to the Frog Pond may detect contaminants moving from the
waste rock pile toward the Frog Pond, the amount of response time the detection
will provide is unknown.
51.
In summary, Ecology has not obtained sufficient information to provide
reasonable assurance that water quality standards will be protected from
leachate discharging from the waste rock facilities.
Aquatic Resources
Mitigation Plan
52.
The proposed mine will result in direct impacts through filling and
excavation to approximately 3.6 acres of wetlands and 8 springs and seeps. In addition, the proposed mine will result
in indirect impacts to approximately 15.15 acres of wetlands and 9 springs and
seeps. The indirect impacts are
primarily from flow reduction from dewatering during mining and from draw down
caused by the post-mining pit lake.
53. These impacts
are addressed under an Aquatic Resources Mitigation Plan (ARMP). Compensation for these impacts is based
primarily on enhancement of downstream wetlands and streams. BMG is not able to provide extensive onsite
mitigation due to resistance of federal agencies that manage the land. The federal agencies are unwilling to make
long term commitments to mitigation measures that might be inconsistent with
their land management priorities. The
direct impacts to Buckhorn Mountain’s headwaters, wetlands, seeps, and springs,
are therefore compensated by off-site and out-of-kind mitigation.
54. The ARMP
focuses on preservation and limited enhancement of off-site resources, not on
actual compensation for or replacement of lost resources. The level of proposed mitigation is
insufficient to compensate for the impacts to wetlands and streams on Buckhorn
Mountain. Many of the resources
proposed for protection or enhancement are already in existence, and are
already protected by existing environmental laws. Since these sites already provide some valuable functions to
aquatic resources, the additional protection of these resources as proposed in
the AMRP provides no real compensation for the impacts from mining operations.
55. Any conclusion
of law deemed to be a finding of fact is hereby adopted as such.
Based on the foregoing findings of fact the board enters
the following
CONCLUSIONS OF LAW
56. The board has jurisdiction in these appeals pursuant to Chapter 43.21B RCW.
57. There is no dispute that the proposed mine will require significant mitigation of adverse impacts to water supplies and water quality. The proposed mine will result in the degradation of nearly 800 acres of mostly public lands. When all is said and done the mine will increase consumptive water use and result in a permanent shift in the hydrogeologic divide between two watershed basins. Both of these basins have been putatively closed to new appropriations of water. For many years Ecology has denied all new water right applications in these basins to preserve adequate stream flows for fisheries. When the mine closes, we will be left with a deep pit lake, two massive waste rock disposal piles and a tailings impoundment facility. The tailings impoundment will smother over 4,200 lineal feet of a headwaters stream. The pit lake is projected to violate state water quality standards from metals leached from the exposed rock walls of the pit. The waste rock piles are also predicted to leach pollutants and will not meet state water quality standards at the toe of the piles.
58. The proposed mitigation, as more fully set forth below, is not legally sufficient to meet the criteria for approval of the water right applications or providing reasonable assurance for the § 401 Certification. The physical knowledge of the affected lands is limited in critical areas necessary to conclude that proposed mitigation water is sufficient or that the water will be delivered in a timely manner to affected streams. The mitigation is therefore highly speculative and uncertain. The same must be said for the permanent engineered solutions offered for the shift in a hydraulic divide. The proposal in essence calls for re-plumbing a watershed with facilities that must be maintained forever. The same is true for the pit lake. The response to predicted pollution in the pit lake is to construct a water treatment plant on top of a mountain that will have to be powered and maintained forever. We are unable to say what will ultimately happen with the waste rock piles. We know that they will pollute the environment. How or in what manner the applicant and state will respond to this pollution is unknown.
59. The only real assurance we have is the proposed bonding that the state may rely on to enforce environment laws in the future. This approach is tantamount to entering a busy interstate highway on an exit ramp against the traffic. The availability of insurance in that circumstance is no more comforting than the proposed bonding here. The focus of our environmental laws must be on preventing pollution and habitat degradation. It is not legally sufficient to proceed with the proposed mine without much more specific knowledge of the potential impacts from the development and meaningful means of preventing and protecting against the adverse consequences of the development. The long-term engineered solutions proposed in this case are legally insufficient.
60. The water right applications are subject to the four-part test under RCW 90.03.290 and RCW 90.44.060.[1] There must be an affirmative showing that water is available for appropriation, the proposed appropriation is for a beneficial use, the appropriation will not impair existing rights, and the appropriation will not detrimentally affect the public welfare. There is no dispute that water is available and will be put to a beneficial use. There is further no dispute that the proposed water rights will result in an impairment of existing rights. This impact is resolved through the mitigation plan approved by Ecology. We conclude that the proposed mitigation is insufficient and, therefore, that the proposed water rights would result in an impairment of existing rights and not satisfy the requirements of RCW 90.03.290.
61. The inadequacy of the mitigation plan rests primarily on the lack of information supporting the scheme. As thoroughly as this proposed mine has been studied and evaluated, it is not at all certain that we have a clear understanding of the hydrogeology on the site. There are substantial questions about the stream flows, ground water flows and relative precipitation. Without more information it is uncertain how much water will be needed for mitigation and when mitigation water will reach intended streams. Further, because post-reclamation mitigation is required in perpetuity to offset the permanent shift in the groundwater divide, the boreholes and treatment facilities required for post-reclamation mitigation must be maintained forever. The speculative and perpetual nature of mitigation proposed here does not meet the requirements that new water rights not impair existing rights or the requirement that new rights not be detrimental to the public welfare. Manke Lumber Co. v. Department of Ecology, PCHB 96-102 (1996).
62. Water quality certifications are required under the following terms of section 401 of the Clean Water Act (CWA) (33 U.S.C. 1341):
Any applicant for a Federal license or permit to conduct any activity including, but not limited to, the construction or operation of facilities, which may result in any discharge into navigable waters, shall provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate that any such discharge will comply with the applicable provisions of 1311,1312, 1313, 1316, and 1317 of this Title.
The state thus certifies that a proposed federal action complies with applicable water quality laws. The federal action at issue here is a dredge and fill permit under section 404 of the CWA (33 U.S.C. § 1344) to develop and operate certain aspects of the mine and mitigation measures related to the mine development. The United States Army Corps of Engineers issued a section 404 permit on June 28, 1999. The Department of Ecology issued its water quality certification on January13, 1999.
63. A § 401 Certification means that the state has reasonable assurance that there will be compliance with water quality laws. Friends of the Earth v. Department of Ecology, PCHB No. 97-64 (1988). Appellants contend that reasonable assurance is not present here because the pit lake will constitute a water of the state and the treatment plan provides for some period of time over which the water quality in the lake must come into compliance with water quality standards. The appellants moved for summary judgment on this issue. Our water pollution laws do not mandate such stringent purity in waters of the state. Waters of the state are broadly defined to include any and all surface water and groundwater. RCW 90.48.020. Water quality regulations recognize the impact of human activity and provide means to allow for reasonable compliance through measures such as mixing zones, WAC 173-201A-100, compliance schedules, WAC 173-201A-140, and, as in this case, alternate points of compliance, WAC 173-201A-060. It would be seemingly impossible to undertake any type of mining or construction without causing some disturbance of soils that might lead to a violation of water quality standards. It is therefore reasonable to establish time periods and boundaries within which a mining activity must come into compliance with applicable standards.
64. We nonetheless conclude that § 401 Certification is unsupported by the record before the board.[2] The only available model predicts that the pit-lake will violate water quality standards. The contingent response to this is to construct a high-altitude water treatment plant that must be powered and maintained in perpetuity. The long term speculative success of a permanent water treatment facility should not replace the protections afforded by our water quality laws. Even more speculative is the projected pollution from the two waste rock facilities. There is significant uncertainty about the characteristics of the pollution, its flow paths, rate of discharge or even the appropriate point of compliance. It is not appropriate to issue a Certification given the lack of information about the extent and fate of contamination from the waste rock facilities. Barrish & Sorenson Hydroelectric Co., Inc. v. Ecology, PCHB No. 94-194 (1995). Under these circumstances the more appropriate conclusion is that there is presently no reasonable assurance to support a § 401 Certification.
65. The § 401 Certification also requires reasonable assurance that any impacts to aquatic resources will be fully mitigated. This requirement is derived from the Washington State anti-degradation policy:
Waters of the state shall be of high quality. Regardless of the quality of the waters of the state, all wastes and other materials and substances proposed for entry into said waters shall be provided with all known, available, and reasonable methods of treatment prior to entry. Notwithstanding that standards of quality established for the waters of the state would not be violated. Wastes and other materials in the substances shall not be allowed to enter such waters which will reduce the existing quality thereof, except in those situations where it is clear that overriding considerations of the public interest will be served.
RCW 90.54.030(3). Our water quality standards similarly emphasize that “existing beneficial uses shall be maintained and protected and no further degradation which would interfere with or become injurious to existing beneficial uses shall be allowed.” WAC 173-201A-070(1). This regulation was adopted pursuant to NPDES permit authority delegated to the State of Washington under the Federal Clean Water Act. 33 U.S.C. § 1313; PUD No. 1 v. State of Washington, 511 U.S. 700, 705 (1994). See RCW 90.48.260.
66. In the context of wetlands the anti-degradation policy is expressed in terms of a goal that there be no net-loss of wetlands. In regulating activities impacting wetlands the department requires a staged analysis and mitigation ratio. O’Hagen v. DOE, PCHB No. 95-25 (1995).
67. The anti-degradation policy does not prohibit all impacts to aquatic resources. Instead, as applied to wetlands, the policy mandates that impacts be avoided, minimized and compensated. It is true that Ecology reduced the direct wetland impacts on-site to 3.9 acres. This required some reconfiguration of the proposed operations. It is not clear, however, what analysis was made of avoiding the impacts altogether. There may be alternative locations for the tailings facilities rather than over 4,200 lineal feet of a headwater stream. However, even if the impacts are unavoidable, the record does not establish that the proposed level of compensation is adequate. The applicant is obviously limited in mitigation options because most of the site lies on publicly owned lands. This severely limits the ability of BMG to provide on-site mitigation. The resulting hodge-podge mitigation plan does not, however, provide adequate mitigation. In general the plan promotes modest improvement and protections to existing resources. The mitigation plan additionally inflates the degree of compensation afforded for the mine. Much of the acreage credited for mitigation is in fact located on uplands. Some credit is due for the extent of mitigation proposed. It is not enough, however, given the overall impact and uncertainties associated with the mine.
68. Any finding of fact deemed to be conclusion of law is hereby adopted as such.
Based on the foregoing findings of fact and conclusions of law the board enters the following
ORDER
The appeals of the water right determinations are hereby GRANTED and the subject Reports of Examination are REVERSED;
The appeals of the § 401 Certification are hereby GRANTED and the same is VACATED.
DATED this 19th day of January, 2000.
POLLUTION CONTROL HEARINGS BOARD
JAMES A. TUPPER JR., Presiding
ANN DALEY, Chair
ROBERT V. JENSEN, Member
PCHB 97-146 Final
[1] Our analysis here, together with the foregoing findings of fact are intended to encompass the remaining issues presented to the board for the 1998 hearing. We do not however, separately address whether a supplemental EIS was required for the streamflow mitigation. Those issues are moot given the board’s ruling today.
[2] Our analysis together with the foregoing findings of fact are intended to encompass all of the remaining issues presented to the board for hearing in 1999. Having reversed the § certification, the board does not address the SEPA issues.