EHO Case Summaries
for the period April - September, 2007
Shoreline Cases
from the SHB
Sterling v. City of Montesano, Paul Willis, Willis
Enterprises and Bowers Construction,
SHB No. 06-110
Order of Dismissal (April 20, 2007).
Willis and Bowers sought a conditional use
permit (CUP) to build commercial office facilities and a warehouse on a parcel
in the City of Montesano adjacent to the Chehalis River. The City issued a
Determination of Non-Significance (DNS) under the State Environmental Policy
Act and approved the CUP. There was no appeal of DNS. Subsequently, Willis
applied to the city for vacation of the undeveloped portions of the plat within
which the office and warehouse were to be built, including vacation of the
rights-of-way. By resolution and ordinance, the City vacated the plat and
rights-of-way, subject to a new plat application that contained a perpetual
easement along the Chehalis River shoreline.
Sterling appealed the City's actions, arguing
that the City was required to amend the 2005 CUP in order to take the street
and plat vacation actions, and that further SEPA review was required. Sterling asserted piecemealing, and inappropriate phased review under SEPA.
The Board concluded that it was without
jurisdiction over the appeal of the City's action to vacate the plat and
related rights-of-way. There was no underlying shoreline permit appeal before
the Board, and the Board rejected the argument that preparation of the area for
possible future development through the vacation of an outdated plat amounted
to inappropriate phasing or piecemealing under SEPA. The Board stated that Sterling showed no linkage between the current actions of the City and the earlier CUP,
sufficient to give the Board jurisdiction.
The Board also rejected the City's assertion
that because Sterling had pursued a LUPA action in Superior Court he had
elected his remedy, and could not appeal to the SHB.
The case was dismissed for lack of
jusrisdiction.
May v. Roberston/Kvinsland and Pierce County,
SHB No. 06-031
Findings and Conclusions and Order (April 2007)
This case involved Pierce County's
approval of a shoreline substantial development permit (SDP) for a proposed
joint use pier, ramp and float (PRF) and a shoreline conditional use permit
(CUP) for a floating watercraft lift on Hale Passage on Puget Sound. The proposed
placement of the PRF structure was in the middle of an unusually long stretch
of unobstructed sandy beach with no other nearby docks. It would extend from
the center of the beach 100 feet into the water.
The Board found the beach and
nearshore area was the site of various marine plants that are important for
juvenile salmon and spawning forage fish. It also found that eel grass beds,
which had been previously destroyed by sediment from earlier development along
the top of a high bank adjacent to the sandy beach, were re-establishing along
the beach in the vicinity of the proposed float lift and along the shore. The
Board also found the beach area in question serves as a migration corridor for
juvenile salmonids and supports various other marine species.
Although the float lift was planned
to be located in the possible vicinity of some newly established eelgrass, the
Board determined the float lift did not otherwise significantly impact the
nearshore environment because it was to be located some distance off shore.
In its decision on the SDP, the
Board considered the proposal's compatibility with the surrounding environment
and other uses. Pierce County's general criteria and guidelines for reviewing
substantial development permits include consideration of compatibility. In
connection with this analysis, the Board considered cumulative impacts of the
project, even though cumulative effects are not specifically listed as criteria
for decisions on SSDPs in the Pierce County Shoreline Master Program. The
Board held that, even though cumulative impacts are not listed per se as
SSDP criteria (as they are for shoreline conditional use and shoreline variance
permits), the Board is not precluded from considering cumulative impacts. The
Board cited its 2000 decision in Viafore v. Mason County, SHB No. 99-033
as support for its conclusion that, in some circumstances, it is
appropriate to consider SDP applications for docks in the context of potential
future development. In so doing, the Board distinguished the facts in May
from its 2006 decision in Roller v. Unger, SHB No. 06-016, where the
Board had held that the Pierce County Code did not require consideration of
cumulative effects, pointing out that the Roller case also did not
preclude such consideration. In Roller, there had been several existing
piers visible from the proposal site and within a short distance. Also, there
was no evidence of any risk of environmental damage present in Roller,
as the Board found was the case in the May proposal.
The Board reversed Pierce County's
decision approving the PRF, and affirmed the County's approval of the CUP for
the floating watercraft lift, but added a condition that a supplemental eel
grass survey be conducted to allow placement of the float lift in a location
that would not impact eelgrass.
The applicants have appealed the
Board's decision to Pierce County Superior Court.
Fladseth v. Mason County
SHB No. 05-026
Findings and Conclusions and Order (May 1, 2007)
This appeal involved Mason County's
denial of a shoreline substantial development permit (SDP) a proposal for a
115-foot joint use pier-ramp-float (PRF) project on the north shore of Hood
Canal in Mason County near Belfair, Washington. The Board affirmed the
County's denial on the basis that the PRF was not consistent with the Mason
County Shoreline Master Program (MCSMP).
The MCSMP recognizes that
additional uses place increasing pressures on the shorelines and that
unrestricted construction on the shores of Mason County is not in the best
public interest. Although there is no specifically-articulated distinction in
the MCSMP between the north and the south shores of Hood Canal the County
asserted that a cumulative effects analysis is required. In its decision, the
County considered the extent of development on both shores of Hood Canal and
the potential cumulative impact of additional over water structures on the
comparatively undeveloped north shore.
The Fladseth's proposal was opposed
by a group of neighbors that formed a non-profit organization created to oppose
the construction of inappropriate permanent structures in the inter-tidal zone
of Hood Canal. The group pointed to the scarcity of such structures on the
north shore, and cited potential adverse impacts to views, public enjoyment of
the tidelands and the environmental quality of Hood Canal and its marine life.
The Board found that the north
shore of Hood Canal in Mason County is relatively undeveloped with docks
compared to the south shore. A biological evaluation (BE) prepared for the
Fladseths discussed potential indirect effects from the project, including the
alteration of nearshore juvenile salmon routes, but did not assess the
potential cumulative effects from increased numbers of docks.
Citing its decision in the May
case (SHB No. 06-031), the Board again concluded that it was not precluded from
considering cumulative environmental impacts, where appropriate. The Board
found that there is a general requirement for cumulative effects to be
considered as part of a SDP for a pier or dock in Mason County on Hood Canal,
which is a shoreline of statewide significance. The Board opined that the
amount of development already present in an area is another important consideration,
and that the potential for future build-out is an important, albeit not
determinative consideration in a cumulative impacts analysis. In affirming
Mason County's denial of the SDP, the Board stated that consideration of
potential cumulative effects and precedential effects is warranted in any case
where there is proof of impacts that risk harm to habitat, loss of community
use, or a significant degradation of views and aesthetic values.
Dagg & Enselman v. San Juan County,
SHB No. 06-037
Order on Summary Judgment (July 19, 2007)
The Daggs and Enselmans applied
together for a shoreline substantial development permit (SDP) from San Juan
County to build a pier-ramp-float (PRF) on Garrison Bay on San Juan Island.�
San Juan County denied the Dagg/Enselman application because the applicants had
not established, as required by the San Juan County Shoreline Master Program that
use of another neighbor's existing dock (located on Lot 94) was "not adequate
or feasible." �The County's decision to deny the Dagg/Enselman application
reflects its strong policy to control the proliferation of docks along its
shorelines.
The applicants, on a motion for
summary judgment before the Shorelines Hearings Board, argued that joint use of
the Lot 94 dock was not adequate or feasible because the owner of Lot 94 had
proposed conditions for joint use that were unreasonable. The history of the Lot
94 dock was brought out through the summary judgment process, where it was
determined that when the Lot 94 dock was permitted and built, the owner had agreed
as a condition of obtaining the permit, to allow joint use by the lots now
owned by Dagg and Enselman "if requested and subject to reasonable terms." This
condition was recorded against Lot 94's deed, but not on the deeds of the
neighboring lots.
The Board concluded on summary
judgment, as a matter of law, the Daggs and Enselmans did have legal access to
Lot 94's dock on reasonable terms because of the condition in the Lot 94
permit. To conclude otherwise, the Board reasoned, would make joint use of Lot
94's dock a fiction, would result in two docks instead of one, and would run
counter to the policy of San Juan County to avoid the proliferation of docks.
The Board declined to rule on
whether the terms of use proposed by the owner of Lot 94 were reasonable. The
Board concluded that it was not the appropriate forum to make this
determination because the permit under appeal, and over which the Board had
jurisdiction, was not the Lot 94 permit, but the Dagg/Enselman application for
a permit. The Board noted that the owner of Lot 94 was not a party to the
appeal of the Dagg/Enselman application and that the dispute regarding the
joint use of Lot 94 is a private dispute between neighbors outside of the
Board's jurisdiction. The Board also noted, however, that the County had a
role to play in resolving this dispute because the County had approved the Lot
94 dock on the condition that joint use be allowed on reasonable terms (and
thereby had enforcement authority and responsibility), and that it had failed
to require the completion of a joint use agreement or recording of the joint
use condition at the time of the original permit.
The Board's decision is on appeal
to San Juan County Superior Court.
Kinzel v. Department of Ecology,
SHB No. 05-007
Findings of Fact, Conclusions of Law and Order (July 20,
2007)
This case involved the appeal of a
civil penalty reinstated after Petitioner failed to fulfill the requirements of
a restoration plan the parties had previously agreed to in lieu of the monetary
penalty. The Petitioner had constructed a rock berm in the Wenatchee River 20
to 60 feet waterward of the ordinary high water mark because he was concerned
about potential erosion of his property. The Petitioner then placed approximately
1,400 cubic yards of fill behind the rock berm. All of this work was done
without permits. The Department of Ecology imposed a $30,000 penalty for these
violations.
The Petitioner, through his
attorney, persuaded the representatives of the local, state, and federal
agencies to allow the Petitioner to restore the shoreline rather than pay the
penalty. The Petitioner hired a landscape consultant to develop a restoration
plan that was eventually approved by the government agencies. Shortly before
the hydraulic project approval was issued by the Department of Fish and
Wildlife to allow the restoration work to commence, the Petitioner decided the
plan was too expensive and discharged the landscape consultant. Petitioner's
attorney withdrew shortly thereafter. Ecology asked the Board to reinstate the
full $30,000 penalty and require the Petitioner to also implement the
restoration plan.
Based upon the evidence at the
hearing, the Board concluded that the restoration plan was not unreasonable or
too expensive. The Board noted that this stretch of the Wenatchee River was
highly valuable because of its use by fish listed as endangered or threatened
under the federal Endangered Species Act. The Board also rejected Petitioner's
argument that the ordinary high water mark was more appropriately determined by
maps depicting elevation levels rather than the vegetation line on-site.�
Although the Board affirmed the entire $30,000 penalty, it suspended all but
$5,000 of the penalty in order for the Petitioner to move forward on the
restoration of the property. The Petitioner has appealed the Board's decision.
Stollar et.al. v City of Bainbridge Island and Ecology,
SHB No. 06-024, 06-027 (Consolidated)
Findings of Fact, Conclusions of Law and Order (September 25,
2007)
Five homeowners of contiguous parcels on the
west side of Bainbridge Island sought review of decisions by the City of
Bainbridge Island and Ecology that denied conditional use permits to build a
common bulkhead at the base of the bluff beneath their homes. The Shorelines
Hearing Board affirmed the denial of the conditional use permits.
The properties sat on a Bainbridge Island bluff,
characterized by the City as one of the most significant feeder bluffs on the
Island. The feeder bluff is approximately 3600 feet long, and contributes a
significant amount of sediment to Puget Sound in the Agate Passage area. It
supports a diversity of biological processes, including off-shore fish
spawning, and a rich near-shore environment. Because the ongoing erosion of
the bluff was resulting in various forms of landslide activity along the bluff,
Petitioners were concerned about the long-term stability of the bluff and
integrity of their homes and some appurtenant structures. They sought to build
a traditional hard-armored bulkhead of approximately 420 feet along the base of
the bluff to protect the toe of the bluff, in order to slow upper bluff erosion
and failure. Petitioners made limited efforts to explore and consider
alternative soft-bank shore protection approaches for their properties.
The Board decision relies on the terms of the
Bainbridge Island Shoreline Master Program (BISMP), which disfavors hard
bulkheads, and places a heavy burden on those seeking to build such a
structure. First, the Board noted that the BISMP prohibits outright shoreline
hardening on shores with valuable geo-hydraulic or biological processes
sensitive to interference and critical to shoreline conservation, such as
feeder bluffs. BISMP 16.12.300 C.4. The Board concluded that the proposed
bulkhead was prohibited under this section, given the unique characteristics of
the area. If not prohibited outright, the Board concluded that the Petitioners
failed to "conclusively demonstrate" that soft shore bank stabilization (such as
use of natural materials or nonstructural solutions) was unworkable to protect
the development on the bluff. This standard is set out in the BISMP. The
Board then concluded, as had Ecology, that Petitioners had not met the
conditional use criteria of WAC 173-27-160, as the proposal was inconsistent
with the BISMP. The Board also noted the likelihood of a detrimental
cumulative impact to the granting of the permit in this case.
The case has been appealed to Thurston County
Superior Court.
Pollution Control
Hearings Board Cases
Community Association for Restoration of the Environment
(CARE) v. Ecology, Northwest Dairy Association (NDA) et. al.,
PCHB 06-057, 055 (consolidated)
Order on Motions; Findings of Fact, Conclusions of Law and
Final Order, (both issued August 1, 2007)
This consolidated case involved
appeals of the Concentrated Animal Feeding Operation National Pollution
Discharge Elimination and State Waste Discharge General Permit (CAFO General
Permit) issued by Ecology. The Appellant and Intervenors challenged numerous
conditions of the permit, including those related to nutrient management plans
(NMPs), soil monitoring, surface and ground water quality monitoring, reporting
requirements, and public access to CAFO records.
The parties brought motions for
summary judgment on many of the legal issues in the appeal. The Board decided,
on summary judgment, that it was reasonable for the permit to require
permittees to update their NMPs when they change the field areas where they
land apply animal wastes, and clarified the timing required for the updates.�
It also decided that the scope and timing of the permit's noncompliance
reporting requirements were lawful and that the permit termination provisions
were lawful. The Board concluded, as a matter of law, the permit did not
eliminate other defenses or discharge authorizations available through other
federal regulations or permit conditions, and that it did not eliminate a citizen's
right to appeal the substantive adequacy of a CAFO's NMP as part of an appeal
of Ecology's coverage decision for an individual CAFO.
The Board directed Ecology to
modify the permit to include a definition clarifying the standards for
establishing land application rates in a manner that is consistent with AKART
requirements. The Board also denied summary judgment on several issues on the
basis that material facts were in dispute or that further development of the
record was needed to resolve the matters.
After the hearing on the merits,
the Board concluded that the CAFO General Permit, with certain clarifications,
complies with applicable federal and state water quality requirements. The
Board found the permit was the product of an open and iterative permit
development process and represents a scientifically sound and reasonable
decision on the part of Ecology. The Board further found the Appellant CARE
failed to prove that the permit's record keeping and reporting provisions
conflict with the public access requirements of the federal Clean Water Act
(CWA) or state laws related to public records and public disclosure. The Board
also concluded that the permit's approach to providing public access to
facility inspection, discharge, and other record information strikes a lawful
balance between allowing interested citizens access to adequate information
while protecting permittees from the disclosure of confidential business
information.
The Board found CARE had similarly
failed to prove the permit's reliance on NMPs based on Natural Resources
Conservation Service (NRCS) standards is either unlawfully vague or ambiguous,
or unenforceable. The Board affirmed Ecology's decision to require NMPs to
conform to NRCS practice standards. Finally, the Board affirmed the CAFO
General Permit's environmental monitoring regime as reasonable and appropriate
and determined that CARE's challenge to the adequacy of the Permit's soil
monitoring requirements, and its request for the Permit to include surface and
groundwater monitoring, were not supported by the weight of the evidence.
CARE appealed the Board's decision
to Thurston County Superior Court, and all parties jointly requested a
certificate of appealability for direct review by the Court of Appeals. The
Board granted the request and issued a certificate of appealability in October.
�The Court has not yet decided whether it will accept direct review.
Mountain West Senior, LLC, and Maddox Construction, LLC,
v Ecology, PCHB No. 06-073 and 06-110 (Consolidated) ----Order on Summary
Judgment (August 15, 2007)
Ecology issued separate penalties to Mountain
West and Maddox for violations of the Construction Stormwater General Permit
and Ch. 90.48 RCW at a construction site in Whatcom County. Mountain West was
the owner of the development project, while Maddox was the general contractor
and site operator. Mountain West obtained coverage under the General Permit
for the construction activity at the site, but Maddox did not.
Maddox argued on summary judgment that it could
not be subject to penalties where another entity is covered by the permit. The
Board rejected this argument and held that Ch. 90.48 RCW does not excuse
discharges in violation of the chapter simply because another entity is covered
by a permit for those same activities. The Board noted that the statute is a
strict liability scheme, and that contractors at a construction site must
comply with RCW 90.48.080 whether or not they are a signatory to the general
permit.
Although the Board concluded that separate
penalties may issue, it noted that there was a question of whether Ecology
could impose a maximum statutory penalty of $10,000 per day per violation
against both the site owner and site operator where they shared in
responsibility for a single discharge violation. The question of whether there
must be joint liability in such circumstance was left unresolved on summary
judgment.
Also unresolved on summary judgment was the
question of whether Maddox, as the operator at the site, could be penalized for
failing to obtain coverage under the General Permit in the first instance. The
Board's decision points out that questions remained as to how Ecology
interpreted and applied the terms of the general permit on the issue of who
(owner or operator, or both) must be covered by the General Permit.
The case has not proceeded to hearing, pending a
final settlement by the parties.