Case Summaries � March 2007
Pollution Control Hearings Board
Squaxin Island Tribe v.
Department of Ecology & Miller Land and Timber, LLC, PCHB No. 05-137
(Modified Findings of Fact, Conclusions of Law and Order) (November 20, 2006).
The Squaxin Island Tribe (Squaxin
Tribe) appealed two Reports of Examination issued by the Department of Ecology
(Ecology) approving applications by Miller Land and Timber, LLC (Miller) for
groundwater withdrawals in an area of Thurston County that was closed to
further consumptive surface water withdrawals by rule.� Woodland Creek, which
is located near the wells that were authorized by Ecology to provide water for
the two proposed residential housing developments in question, is in hydraulic
continuity with the groundwater.
The Squaxin Tribe is a signatory to
the Medicine Creek Treaty.� Henderson Inlet and the Woodland Creek basin are
within the Tribe�s usual and accustomed fishing area.� The Squaxin Tribe
contended that the groundwater withdrawals would pull water from Woodland Creek
and negatively impact their treaty rights in fish, particularly with regards to
coho salmon.� As a condition for approval of the proposed withdrawals, Miller
was required to provide stream augmentation from June 1 to November 1 in
perpetuity or until on-site withdrawals ceased.� Ecology and Miller asserted
that the approved proposals would actually be more beneficial to fish within
the basin because Miller would be pumping groundwater into the creek at a time
when surface flows are naturally lower and the temperatures are warmer.�
Furthermore, if municipal water became available, Miller or its successor was
required to relinquish its water rights and hook-up to the municipal supply.
The Squaxin Tribe moved for summary
judgment on whether Ecology was required to adopt rules to establish a process
to consider the adequacy of mitigation proposals.� The Board found that Ecology
could consider mitigation proposals in the absence of rules for the purpose of
conditioning water rights because the statutory four-part test for approval of
a water right provided sufficient guidance to Ecology.� (Order on Motions)(May
19, 2006).
As part of its summary judgment
motion, the Squaxin Tribe also requested the Board to clarify the appropriate
standard for determining whether water was �available� for appropriation.� The
Tribe advocated that the Board should apply the standard set forth in Postema
v. Pollution Control Hearings Board, 142 Wn.2d 68, 94 (2000).� In Postema,
the Washington Supreme Court stated that a proposed groundwater withdrawal that
is in hydraulic continuity with a closed stream or lake must be denied if �the
withdrawal will have any effect on the flow or level of the surface
water.� (emphasis added).� The Squaxin Tribe also asked the Board to assign the
burden of proof to Ecology to determine whether the permits complied with the
statutory provisions of the Water Code and WAC Chapter 173-513.
Ecology and Miller asserted that
the proper standard for determining �availability� was contained in WAC Chapter
173-513, which applies to the Deschutes River Watershed in which Woodland Creek
is located.� Postema is distinguishable, they argued, because it was
based upon a specific standard contained in the rule pertaining to the Puyallup River Basin.� Both Ecology and Miller noted that WAC Chapter 173-513 does not
prohibit all groundwater withdrawals.� WAC 173-513-050 provides that �Future
ground water withdrawal proposals will not be affected by this chapter unless
it is verified that such withdrawal would clearly have an adverse impact
upon the surface water system contrary to the intent and objectives of this
chapter.�� (emphasis added).�� Both Ecology and Miller also argued that it
would be inappropriate for the Board to shift the burden of proof away from the
Appellant.
The Board began its analysis of WAC
173-513-050 by recognizing it prohibited groundwater withdrawals if there was a
clear adverse impact upon the surface water system contrary to the intent
and objectives of this chapter. (emphasis added).� The stated purpose for
closing the Deschutes River Basin from further consumptive appropriation, as
set forth in WAC 173-513-020, was to provide sufficient instream flows
�necessary to provide protection for wildlife, fish, scenic, aesthetic,
environmental values, recreation, navigation, and water quality.�� The Board
also noted that WAC Chapter 173-513 was adopted pursuant to the Water Resources
Act (Chapter 90.54 RCW) and the statutes governing minimum water flows and
levels (Chapter 90.22 RCW).� Both RCW 90.54.020 and 90.22.010 contain similar
language about the need to retain flows for the protection of wildlife, fish,
scenic, recreational, aesthetic, environmental values, and navigational values.
Turning to the Postema
decision, the Board recognized that the Supreme Court quoted the language from
RCW 90.54.020, which evidenced the need to provide protection for the
environmental values listed.� The Board then reconciled the �clear adverse
impact� language from WAC 173-513-050 with the �any effect� language used by
the Supreme Court in Postema by finding that Miller�s groundwater
withdrawals would constitute a clear adverse impact and be subject to the
rule�s prohibition, if the withdrawals produced any effects which adversely
impacted the values that were set forth for protection in WAC 173-513-020.� The
Board also rejected the Squaxin Tribe�s request to shift the burden of proof in
this case.
In the hearing on the merits, the
Board was faced with competing hydrologic models.� Miller�s hydrogeologist used
a model developed by the United States Geological Survey for Thurston County.� The Squaxin Tribe�s hydrogeologist relied upon a model that was much more
site specific.� The Board found that the site-specific model was more
persuasive.� This model showed that water would be pulled from Woodland Creek
during the summer months to the detriment of fish.� The Board concluded that
water was therefore not available and that the proposed withdrawals were not in
the public interest within the meaning of RCW 90.03.290.� The Board also found
that the Reports of Examination were inadequate on other grounds, including the
lack of baseline conditions being established in order to assess how the
tributary and wetlands would be impacted by the withdrawals.� This assessment had
been recommended by the Washington Department of Fish and Wildlife pursuant to
its small stream policy (Policy 5204).� The Board vacated Ecology�s decisions
but left open the possibility of a preliminary permit being issued to further
assess the actual effects of the groundwater withdrawals.� The Squaxin Tribe
and Miller have filed cross appeals in Thurston County Superior Court.� �
Puget Soundkeeper Alliance and Northwest Marine Trade
Association v. Ecology,
PHCB Nos. 05-150, 05-151, 06-034, 06-040
Findings of Fact, Conclusions, Order (January 26, 2007)
These consolidated appeals
challenged the Boatyard General National Pollutant Discharge Elimination System
(NPDES) Permit No. WAG-030000 (Permit) issued by Ecology to regulate stormwater
runoff from boatyards in Washington.� The Puget Soundkeeper Alliance (PSA)
contested the lack of numeric effluent limits for stormwater discharges of
metals and other pollutants and disputed the methodology Ecology used to set benchmark
levels for copper.� PSA also questioned the adequacy of the Permit�s monitoring
and response provisions and argued the adaptive management scheme was not adequately
enforceable.� The Northwest Marine Trade Association (NMTA) opposed certain required
best management practices (BMPs) and other requirements in the Permit that were
more stringent than the previous Permit.
����������� The Board concluded that the law does not
mandate the use of numeric water quality based effluent limits in a general
stormwater permit.� The Board upheld Ecology�s general approach of using
effluent benchmarks, BMPs, and adaptive management to regulate stormwater
discharges under the Permit.� However, the Board found flaws in the methodology
used to calculate the copper benchmarks, and other provisions of the Permit, that
require modification to assure compliance with water quality standards.
����������� Ecology derived the copper benchmarks by
calculating starting with the state water quality criteria for copper and then
applying numeric values for various mitigating factors, including a water
effects ratio (WER), a dilution factor, and a dissolved/total recoverable
metals translator.� The Board found flaws in Ecology�s use of two of the
mitigating factors.� The use of a standard dilution factor by Ecology created
the equivalent of a standard mixing zone, which the Board had previously disallowed
in Industrial Stormwater General Permit appeal (Puget Soundkeeper Alliance
v. Ecology, Order Granting Partial Summary Judgment, PCHB Nos. 02-162,
02-163 & 02-164 (2003)).� The Board noted that Ecology failed to
demonstrate the standard prerequisites for establishing a mixing zone (such as
compliance with AKART, and supporting information indicating a mixing zone
would not cause a loss of habitat, substantially interfere with existing or
characteristic uses of the water body, result in damage to the ecosystem, or
adversely affect public health), and that, in fact, the boatyards, as an
industry, demonstrated widespread lack of compliance with AKART.� The Board
found that use of a dilution factor under these circumstances was error.
����������� The translator value used in calculating the
copper benchmark was based on samples from shipyards, rather than boatyards.�
The Board concluded that some important differences between the two types of
facilities were not accounted for in the use of this data, which led to a translator
that was unreasonably low.� The result was also inconsistent with a large body
of scientific data addressing average dissolved copper readings from urban
stormwater.� The Board directed Ecology to recalculate the translator value on
remand and to also consider the lethal and sub-lethal effects on salmonid
species of discharges at the copper benchmark levels, which Ecology
acknowledged it had not done during development of the permit.
Rather than set separate benchmarks
for lead and zinc, Ecology used copper as an �indicator� or substitute for
specific benchmarks for zinc and lead.� The evidence failed to support
Ecology�s assumption that boatyard discharges had a fixed relationship and relatively
constant ratio of copper to lead and zinc.� Accordingly, the Board held that
Ecology should analyze lead and zinc discharges separately from copper, and
establish appropriate effluent limits and monitoring requirements for lead and
zinc.� In addition, the Board required that the Permit be clarified to indicate
waters currently on the �303(d) list for lead are included in the coverage
(including Lake Union) and that an effluent limit for lead be established for
these waters.�
����������� The Board found the adaptive management approach
in the Permit was an acceptable general strategy for achieving compliance with
water quality standards.� Certain modifications to the adaptive management
provisions of the Permit were required to assure the program would be effective.�
Ecology was instructed to modify the Permit to compel implementation of the
remedial actions dictated by the three response levels in the adaptive
management program.� Further, Ecology was ordered to include a provision in the
Permit addressing the actions that would be required if implementation of the
adaptive management program still failed to result in compliance with
applicable benchmarks.� The decision also orders Ecology to include additional
details in the Permit clarifying timing issues and exceedance triggers.
����������� The Board found certain aspects of the
monitoring and sampling provisions of the Permit inadequate and ordered a
modification to include collection of receiving water samples from some or all
covered boatyards for the purpose of obtaining data for use in evaluating the
assumptions used in establishing the current Permit and future permits.�
����������� The Board largely upheld the BMPs identified in
the Permit, but did grant NMTA�s challenge to the absolute prohibition of non-vacuum
grinders.� The evidence established that in certain limited circumstances it is
impractical to use a vacuum grinder, and the Board concluded that the Permit
should be modified to allow an exception in such situations.� The Board�s
decision remanding the case to Ecology for Permit modification was appealed to
Thurston County Superior Court by both the PSA and NMTA.� The parties
subsequently agreed to a settlement and withdrew their appeals.
Argent Chemical Laboratories, Inc. v. Ecology,
PCHB No. 06-028
Order Granting Partial Summary Judgment (August 31, 2006).
Argent Chemical Laboratories, Inc.
(Argent Labs) appealed a penalty and an administrative order issued by the
Department of Ecology (Ecology) for alleged violations of sections of the
dangerous waste regulations in handling certain liquid material containing
acetone at their site.
Argent Labs had filed an
Application for Relief from penalty with Ecology in order to have the amount of
the penalty reduced.� After Ecology issued its Notice of Disposition upon
Application for Relief denying any mitigation of the penalty, Argent Labs
appealed both the penalty and the administrative order to the Pollution Control
Hearings Board (Board).� The appeal of the administrative order was filed with
the Board sixty-four days after it was issued.� Ecology moved for partial
summary judgment on the basis that the appeal of the administrative order was
not timely filed.
Ecology maintained that the filing
of an Application for Relief for the potential mitigation of a penalty does not
affect the time period for filing an appeal of an administrative order with the
Board.� Argent Labs asserted that since the administrative order and the
penalty all arose out of the same set of facts, it was appropriate to stay the
administrative order pending review of the penalty.
The Board noted that the right to
appeal a penalty and the right to appeal an administrative order are different
processes.� The notice of penalty issued to Argent Labs informed them of their
right to either file an appeal directly with the Board or to file an
Application for Relief with Ecology.� RCW 43.21B.300(1) specifically authorizes
a party to request remission or mitigation of a penalty within 30 days of
receipt of the penalty.� After receipt of Ecology�s Notice of Disposition upon
Application for Relief, a party then has 30 days to appeal this determination
to the Board under 43.21B.300(2).� In contrast, RCW 43.21B.310(1) requires
appeals of administrative orders to be filed with the Board within 30 days of
their receipt. �There is no option of appealing such an order to Ecology.� In
addition, the administrative order contains language stating that the appeal of
the order alone will not stay its effectiveness.� The Board granted summary
judgment to Ecology and dismissed the appeal of the administrative order as
untimely.
I-5 Properties, Jansen, Inc., & Al Jansen v. Ecology
PCHB 05-063
Findings of Fact, Conclusions, Order (February 12, 2007)
The PCHB affirmed the imposition of
an $82,000 penalty against I-5 Properties for numerous violations of the 2000
Construction Stormwater General Permit over a several month period.� The Board
found that the business had prepared an inadequate Stormwater Pollution
Prevention Plan (SWPPP) in the first instance, failed to install initial stabilization
and structural Best Management Practices (BMPs) necessary to control turbid
runoff from the 72 acre site, and also failed to install additional corrective measures
in response to deteriorating site conditions.
As a result, there were multiple
days on which turbid discharges exceeded state water quality standards, with
muddy runoff flowing into a salmon spawning tributary.� Appellants did not
contest the exceedances.� The Board concluded that the business demonstrated a
lack of reasonable diligence in complying with permit terms, by not informing
itself of permit requirements and failing to implement necessary or effective
BMPs across the site over an extended period of time.� In affirming the penalty
amount imposed by Ecology, the Board also noted that the business demonstrated
�a troubling disregard of responsibilities under the permit� by not keeping
records of actions at the site, and failing to produce records requested by
Ecology. �
The Board also disagreed with the
property owner�s main defense, that the enforcement action was barred on the
basis that Ecology had taken control of the site or created a special
relationship under the public duty doctrine through its technical assistance
and informal efforts to help bring the permittee into compliance. �The Board
concluded that the public duty doctrine had no application to Ecology permit
enforcement actions such as this, and that permittees are not shielded from
liability when a regulatory agency provides technical assistance or other
efforts to help bring a permittee into compliance.� I-5 Properties has appealed
this decision to Whatcom County Superior Court.
Shorelines
Hearings Board
Citizens to Preserve the Upper Snohomish River Valley, Highberger, Fenimore, Wolf v. S-R Broadcasting, Skotdal Bros. LLC and Snohomish County,
SHB No. 06-022
Findings of Fact, Conclusions, Order (December 26, 2006)
S-R Broadcasting, the owner and
operator of radio station KRKO AM 1380, was granted a Shoreline Substantial
Development Permit (SSDP) to construct four free-standing radio transmission
towers on a parcel of unimproved property in the Upper Snohomish River Valley.� The towers were necessary for S-R Broadcasting to meet the goal of increasing
its coverage area to include more of Snohomish County, as well as Snohomish County residents commuting to Seattle and Bellevue.� The towers are proposed to be
located more than 700 feet from the Snohomish River, but due to their location
within the floodplain, the project was considered within shoreline jurisdiction
under the Snohomish County Shoreline Management Master Program (SMMP).� The
project site is in an agricultural area of the valley floor, across the Snohomish River from a popular wildlife park (Bob Hiermann Wildlife Park).� The towers would be
visible from certain locations within the park as well as from a number of hillside
homes in a residential neighborhood situated above the valley floor.
����������� The project had a lengthy procedural history at
the local level, which included the withdrawal of the initial application and
re-application of a revised proposal.� As part of that process, the County
initially issued a Determination of Non Significance (DNS).� An Environmental
impact Statement (EIS) was later prepared at the direction of the Hearings
Examiner to address view and aesthetic impacts of the proposal. The EIS was
appealed, and an addendum was subsequently issued.
����������� Citizens to Preserve challenged both the DNS
issued in connection with the towers and the adequacy of the EIS prepared on
the view/aesthetics issue.� The DNS was reviewed under the clearly erroneous
test, and the Board concluded the quality and quantity of information before
the Board was adequate to evaluate any adverse environmental impacts.� The
Board found insufficient evidence to conclude that wildlife, recreational
interests, or river uses would be significantly impacted by the towers.� No
error on the DNS was demonstrated.
����������� As to the EIS, the Board used the rule of reason
standard to evaluate the adequacy of the document and concluded the detailed
analysis of view and aesthetic impacts contained in the EIS was sufficient to
identify and address the project�s impacts on all relevant user groups.� A
visual impacts study had been prepared assessing views from 27 separate
viewpoints, but Citizens to Preserve challenged the methodology used in the
study.� The Board concluded that the visual impact analysis properly
characterized an impact as more than moderate if the view changed from high
quality to low quality.� Citizens to Preserve contended the study should
capture lesser changes to existing views, but the Board upheld the visual
analysis methodology as a sound way to distinguish between moderate impacts and
significant impacts on views.�
����������� Citizens to Preserve raised a number of
challenges alleging the project was inconsistent with the Shoreline Management
Act (SMA) and the SMMP.� The shoreline of the Snohomish River is considered a
shoreline of statewide significance, and Citizens to Preserve contended the
project approval failed to adequately implement several of the priorities for
shorelines of statewide significance (e.g., preserving the natural character of
the shoreline, providing long-term over short-term benefit, and protecting the
resources and ecology of the shoreline).� Similar concerns arose from
provisions of the local master program.� The Board found that the project would
have very little impact on any natural element of the shoreline or resources or
ecology of the shoreline since the towers would be located on farmland over 700
feet from the river�s edge.� The vegetation conditions on the permit would
actually enhance the riparian area at the property�s waterward border.� The
Board concluded the improved radio coverage and the availability of enhanced
local and emergency information services in the area resulting from the project
would be a long term benefit to citizens in Snohomish County.� Citizens to
Preserve argued that the SMMP policy to leave undeveloped those areas which
contain a unique or fragile resource would be violated by allowing construction
of the towers.� The Board acknowledged the picturesque rural landscape of the Upper Snohomish River Valley, but found no basis to find the area a unique or fragile
resource.
����������� Snohomish County based its approval of the
towers proposal, in part, on the Utilities provisions of its SMMP, which allow
utility installations in the rural shoreline environment applicable to this
site.� The Board concluded that S-R had designed the project to comply with the
conditions for utility installations, including as much mitigation of view
impacts as possible.� While the towers would be visible from a number of
locations on the valley floor, as well as from homes in the hillside
neighborhood, every effort had been made to minimize visual intrusion through
paint colors, open tower design, lack of guy wires, and limited lighting.� The
towers would be present in some views, but the views would not be blocked and
no vista would be significantly reduced.
The Board also rejected Citizens to
Preserve�s argument that the permit should be denied because the use was not
water-surface nor shoreline dependent and would permanently alter the shoreline
and conflict with or preempt other shoreline dependent uses.� The evidence
demonstrated that AM radio towers do not need to be near fresh water to
adequately propagate a signal, however, they do need to be located in
conductive soil which in this area is found primarily in the Snohomish River Valley.� Since the entire floodplain is designated as a shoreline, from an engineering
standpoint, a location within the shoreline was necessary to accomplish the
goal of greater radio coverage.� In addition, the Board concluded the antennae
would not conflict with or preempt other shoreline dependent uses, such as
fishing and boating.
����������� Citizens to Preserve also contended that the
project was incompatible with several policies governing agriculture and
activity in the rural environment.� The Board found that the presence of the
towers would not interfere with agricultural production or activity on the vast
majority of the project site or on any of the surrounding properties.� Concern
was expressed that destination farming activities would be diminished by the
intrusion of towers in the visual landscape.� The Board found this alleged harm
was speculative, and outside the type of concerns addressed by Snohomish County�s agricultural policies.
����������� Citizens to Preserve alleged conflicts with several
other policies from the SMMP enunciating broad goals and aspirations for
shoreline development.� The Board found no basis for denying the permit based
on these broad policies, particularly in light of the significant efforts to
minimize and mitigate the project�s impacts.� Finally, a challenge to Snohomish County�s decision to administratively process the revised application was
rejected on the basis that the county code provided it discretion to determine
whether a Hearing Examiner proceeding should be used.
����������� The Board ruled that the permit was properly
issued, despite the fact that certain of the visual impacts could not be fully
mitigated.� Citizens to Preserve appealed the Board�s decision to Thurston
County Superior Court, then later withdrew its appeal.
Stanford v. San Juan County,
SHB No. 06-004
Findings of Fact, Conclusions, Order (September 20, 2006)
This case involved the appeal of
San Juan County�s denial of a shoreline substantial development permit to build
a joint use dock on the west side of Deer Harbor.� The proposed dock, if built,
would have been the only dock along 700 feet of shoreline.� The main use for
the dock was to moor the applicants� 47 foot boat, and the primary issue in the
appeal was whether alternative moorage was available.
The San Juan County Shoreline
Master Program (SJSMP) reflects a policy choice by the County to control the
proliferation of docks along the shorelines of its islands.� A key way it does
this is by directing that dock applications shall not be approved unless the
applicant can show that alternative moorage is not adequate or feasible.� Applicants
in this case argued both that nearby marinas did not have large enough slips
available at the time of their application and that, at their preferred marina,
parking was so difficult that it would render the moorage inadequate/infeasible
even if it became available.
To evaluate the alternative moorage
issue in this case, the Board turned to its prior decisions establishing a test
for �adequate or feasible� which included whether the alternative was �capable
of being used.�� Inskeep v. San Juan County, SHB No. 98-033 (1999)(CL
IV).� �The Board further opined that the concept of availability involves a
temporal dimension.� The appropriate time frame suggested by the San Juan
County Hearings Examiner, and concurred in by the Board, was whether moorage
was �presently available or likely to become available within a reasonable
waiting period.�� The Board further clarified that the length of a reasonable
waiting period would depend on the facts of a particular case, including
consideration of the time of year and size of the boat.
Based on the evidence introduced at
the hearing, the Board concluded the applicants had failed to prove that
alternative moorage was unavailable or likely to come available within a
reasonable waiting period.� The Board found there had been multiple
opportunities throughout the relevant time period (from the date of application
to the date of the Board hearing) for the applicants to obtain commercial
moorage at several different local marinas.� The Board also concluded that,
while parking at the preferred marina may be challenging at peak times of day
during the peak of boating season, Petitioner had failed to show parking would
be so much of an obstacle as to make moorage at that marina unusable.� The
applicants appealed the Board�s decision to San Juan County Superior Court, and
the Court subsequently upheld the Board�s ruling.
Valero Logistics Operation, LP. et.al., v. City of Tacoma
and Pioneer Cay Developing, LLC.,
SHB No. 06-001
Findings of Fact, Conclusions, Order (July 19, 2006)
����������� This appeal involves the somewhat unique
situation of a proposed residential and commercial shoreline development in a
highly industrialized area.� The project proponent, Pioneer Cay, was granted a
shoreline substantial development permit to build an eight-story mixed-use
building on the east side of the Thea Foss Waterway in the City of Tacoma, with
the bottom two floors planned for water-related commercial uses, and the upper
six floors planned as residential condominiums.� The project site is surrounded
by commercial and heavy industrial uses.� The neighboring industries appealed
the City�s approval on the grounds that the proposed development was
incompatible with their industrial uses.� The industries� primary concern was
that future condominium owners would complain about impacts from the adjacent,
pre-existing industrial uses which would result in new restrictions being
placed on their activities/operations.
The City of Tacoma had previously undertaken
an extensive planning process for the Thea Foss waterway with the aim of
redeveloping and revitalizing the area.� The process culminated in the creation
of the Thea Foss Waterway Design and Development Plan, which both recognized
the importance of existing industrial uses and encouraged new commercial and residential
uses.� Consistent with the Plan, commercial and residential uses were authorized
in this area of the Thea Foss waterway under the City�s SMP, but new
development was required to be designed and conditioned to minimize conflicts
with existing industrial uses.
The Board concluded that the Pioneer
Cay project, with some minor additional conditions, was appropriately designed
and conditioned to minimize conflicts with the neighboring uses (noting, for
example, that the building was oriented away from the industrial uses, had a
sky bridge connecting it to an offsite parking garage and only one driveway to
minimize pedestrian/truck conflicts, included striping along the adjacent
street to identify a pedestrian walkway, and would use special wall construction,
duct lining, and specially rated windows to minimize noise impacts).� The Board
also concluded that neighboring businesses had not identified any particular
aspect of the Pioneer Cay project that made it potentially more incompatible
with their industrial use than any other proposed residential use in this
location.
The Petitioners also challenged the
City�s determination under the State Environmental Policy Act (SEPA) that the
project would not have significant impacts on the environment.� Here again, the
main argument was that the project was not compatible with the surrounding
industrial environment.� The Petitioners alleged that impacts from the
surrounding industrial area would negatively impact the proposal.� The Board
concluded that SEPA requires consideration of a proposal�s impact on the
environment, not the surrounding environment�s impact on the proposal.� The
Board also rejected the claim that the project had been impermissible
piecemealed under SEPA simply because a marina had been dropped from the
original proposal, since the mixed-use building constituted a stand-alone
project that could proceed without the marina.� Additionally, because the
parking garage was not allowed to proceed prior to the resolution of the
shoreline substantial development permit for the rest of the project, even
though it was located outside the shoreline jurisdiction, the Board concluded
no improper segmentation had occurred.
The shoreline substantial
development permit for the Pioneer Cay project was approved with some
additional conditions.� The Board�s decision was not appealed.