April 2005
The following summarizes some of the cases
decided in the winter and early spring 2005 by the various boards that make up
the state�s Environmental Hearings Office, in particular the Shorelines
Hearings Board (SHB) and the Pollution Control Hearings Board (PCHB). This summary was prepared by Bill Clarke, a
member of the Pollution Control Hearings Board and Shoreline Hearing Board, and
Kay Brown, Administrative Appeals Judge for the Boards.
I. Pollution Control Hearings Board
A. Standing
Olympia and Vicinity
Building and Construction
Trades Council and Affiliated Unions v. Department of Ecology and Cardinal FG
Co., PCHB 04-147, Order on Motion to Dismiss for Lack of Standing (January 20,
2005).
The Olympia
and Vicinity Building
and Construction Trades Council and Affiliated Unions (�OBCT�) appealed the
issuance of a prevention of significant deterioration permit by the Department
of Ecology for a glass plant in Lewis
County. Respondents moved
to dismiss the association of unions on the basis of lack of standing.
The Board, in analyzing the standing
arguments, applied the three-part test outlined by the court in International Ass�n of Firefighters, Local 1789 v. Spokane Airports, 146 Wash.2d
207, 213-214, 45 P.2d 186 (2002). This test has been identified by the court as
the proper test to use to determine the standing of an association. For an
association to establish standing it must show that: (1) the members of the organization
would otherwise have standing to sue in their own right; (2) the interests that
the organization seeks to protect are germane to its purpose; and (3) neither
the claim asserted nor the relief requested requires the participation of the
organization�s individual members.
The Board concluded that the first prong of
the test (establishment of individual members� standing) could be accomplished
by demonstrating (a) the governmental action causes a specific and perceptible
injury-in-fact that is immediate, concrete and specific, and (b) the interest
the individual seeks to protect falls within the zone of interest that the
environmental statute is designed to protect. Save a Valuable
Environment v. Bothell, 89 Wn.2d 862, 865-68, 576 P.2d 401 (1978). OBCT
was able to meet this prong by establishing impacts on some of their individual
members through their declarations. The Board held that OBCT met the second
prong of the test by establishing that it was within the purpose of their
organization to act on behalf of affiliated labor organizations and their
membership in regulatory and judicial spheres on matters of environmental conditions
affecting work, home and community. Finally, the Board concluded that the third
prong of the test would rarely, if ever, be an issue at the Board, because this
prong is applicable where an association seeks money damages on behalf of
individual members, and damage claims are not cognizable before the Board.
B. Collateral Estoppel
Methow Valley Irrigation District v. Department of Ecology and Okanogan Wilderness League, PCHB 04- 005, Summary Judgment
(November 16, 2004).
Ecology issued orders to Methow Valley Irrigation District (�MVID�) in 2002 reducing
its allowed diversion of water from the Twisp and Methow
Rivers on the basis that
higher diversions constituted the waste of water prohibited under the water
code. MVID appealed these orders to the PCHB in 2002. In 2003, the Board issued
a decision affirming the waste orders and ordering Ecology to issue a supplemental
order reducing waste based on availability of public funding sources. MVID appealed
the Board�s order to Okanogan County Superior Court. Ecology then issued a
supplemental order further reducing MVID�s authorized
diversions. MVID appealed this supplemental order to the PCHB. In its appeal,
MVID raised a number of issues or defenses that it had raised in its appeal of
the 2002 waste orders. Ecology and the Okanogan Wilderness League (�OWL�) filed
motions seeking to prohibit certain issues or claims from being raised on the
basis of collateral estoppel.
The doctrine of collateral estoppel prevents re-litigation of issues between the same
parties if the issues were actually litigated and decided in a prior case by a
competent tribunal. Under Washington
law, collateral estoppel can be applied to
quasi-judicial or administrative proceedings. The PCHB has applied principles
of collateral estoppel to prevent re-litigation of
issues previously decided between the same parties. Friends of the Cowlitz v.
Department of Ecology and City of Tacoma, PCHB 03-100, Order Granting Partial
Summary Judgment (January 14, 2004); Weyerhaeuser v. Tacoma Pierce
County Health Dept. PCHB
99-067 et al., Amended Summary Judgment and Order of Dismissal (March 2, 2000).
Four criteria must be met before collateral estoppel
is applied to preclude re-litigation of an issue: (1) the issues decided in the
prior adjudication are identical with the ones presented in the current case; (2)
there was a final judgment on the merits; (3)� the
party against whom collateral estoppel is plead was a
party in the prior adjudication; and (4) the application of the doctrine will
not work an injustice. Hadley v. Maxwell, 144 Wn.2d 306, 311,
27 P.3d 600 (2001), Reninger v. Department of Corrections,
134 Wn.2d 437, 449, 951 P.2d 782 (1998). The party asserting application of the doctrine
of collateral estoppel bears the burden of proving
all of its elements. State v. Vasquez, 109 Wn. App. 310, 314-15, 34 P.3d 1255 (2001). The Board determined that many of the issues
raised by MVID in its appeal were decided in the appeal of the 2002 order, were
on appeal to Okanogan County Superior Court, and thus could not be raised again
in the 2003 appeal.
C. NPDES Permits and Enforcement Authority
Jay
Rude v. Department of Ecology, PCHB 04-044, Findings of Fact, Conclusions of
Law, Order (December 14, 2004).
This appeal involved the revocation of a
wastewater treatment plant operator�s license at McNeil Island
Corrections Center
(�MICC�). The treatment plant at MICC malfunctioned over a weekend, causing a
spill of sewage sludge. The operator in charge of the facility took certain actions
to determine the cause of the spill and to perform minor cleanup, but did not
contact Ecology regarding the spill. The NDPES permit for the facility included
a standard general provision that Ecology be contacted if a spill occurs. MICC
had conflicting policies regarding the chain of command for communication at
the treatment plant based on prior whistleblower incidents relating to NDPES permit
compliance.
Ecology revoked the operator�s wastewater
treatment license for one year based on negligence due to its communication policies
and failure to comply with reporting provisions in the NDPES permit. The Board
affirmed Ecology�s revocation, finding that, while MICC�s
unclear lines of communication did not support the revocation for negligence,
Ecology�s revocation based on failure to follow permit terms was proper.
Port of Seattle v. Department of Ecology,
PCHB 03-140, Airport Communities Coalition et al. v. Department of Ecology and
Port of Seattle, PCHB 03-141, 03-142, Findings of Fact, Conclusions of Law,
Order (October 18, 2004).
This case was an appeal of the NDPES permit
issued to Port of Seattle�s Sea-Tac International
Airport by Ecology. The
appeal raised a number of issues, including the validity of compliance
schedules and AKART (all known, available and reasonable treatment) analysis,
adequacy of monitoring, designation of wetlands receiving stormwater
as waters of the state, and classification of Sea-Tac Airport�s water treatment system. Sea-Tac
Airport covers
approximately 2,500 acres, and has both industrial wastewater and stormwater collection systems. The industrial wastewater system
area generally coincides with the airport terminal area. Within this area,
airplanes are treated with de-icing fluids during certain weather events. These
de-icing fluids exert high level of Biological Oxygen Demand (�BOD�). Water
from the industrial wastewater area is collected and sent to an industrial
wastewater treatment plant. The runway area and other parts of the airport
contribute stormwater. Stormwater
from the North airport area goes to Lake
Reba and Miller Creek,
while stormwater from runway and South airport area
goes to Northwest Ponds and Des Moines Creek.
On summary judgment (July 2, 2004), the
Board determined that the discharge from the industrial wastewater treatment
plant are wastewater, not stormwater discharges subject
to the schedules in 33 U.S.C. �1342(p)(4)(A). After a
five-day hearing, the Board determined that the permit did not comply with
AKART requirements and the proper relationship between technology based and
water quality based standard, including the proper analysis of the BOD level
threshold for diverting water to King County�s South Treatment Plant (�STP�) in
Renton instead of to the airport�s marine outfall. Airport Communities
Coalition et al. challenged the compliance schedule allowed for sending BOD wastewater
to the King County STP.
Ecology had previously indicated that the BOD pipeline would be constructed by
2004, but this did not occur. The Board determined that even though Ecology had
failed to require AKART in the �shortest, reasonable period of time,� the 2004
NDPES Permit, not previous permits, was the basis for the appeal and that
deadlines from previous permits could not be subject to appeal now.
The Board determined that Sea Tac Airport�s
industrial wastewater treatment plant is not a �publicly owned treatment works�
under the Clean Water Act, based on Ecology definitions used to implement the
CWA. TheBoard determined that structural and
operational changes to Sea-Tac Airport,
and the Stormwater Pollution Prevention Plan were
sufficient to meet BMP-based requirements. The Board determined that Ecology
had concluded Lake
Reba is not a water of
the state without performing a wetland delineation or
other technical evaluation. The Board remanded the permit to Ecology for a number
of further actions, including performing a new AKART analysis, developing a new
compliance schedule for the industrial wastewater treatment plant, revising the
receiving water study, modifying acute and chronic toxicity testing
requirements, and establishment of a mixing zone will be based on the revised
AKART analysis.
II. Shorelines Hearings Board
Preserve
Our Islands et al. v. King County and Northwest Aggregates, SHB 04-009, 04-010,
Summary Judgment (August 10, 2004), Findings of Fact, Conclusions of Law, Order
(November 3, 2004).
The Board reversed King
County�s decision denying shoreline
permits to Northwest Aggregates for a barge loading dock on the eastern shore
of Maury Island. A sand and gravel pit at the
site operated during the 1960s and 1970s using a conveyor and barge to move
sand and gravel from the island. Barging of sand and gravel ceased in the late
1970�s. The gravel pit owner sought permits to renew sand and gravel barging,
including shoreline permits for reconstruction of an existing but
non-functional conveyor and barge loading dock. The Board initially ruled on
several of the multiple issues identified by the parties on summary judgment. King County
moved to dismiss the appeals on the basis that the owner of the aquatic lands
at issue, the Washington Department of Natural Resources, had not been named or
served. The Board, in rejecting this argument, opined that there is no
provision in the Shoreline Management Act (�SMA�), Ecology�s SMA rules, or
Shoreline Hearings Board rules requiring that a property owner be included as an
indispensable party or that they be served. The Board also ruled that it had
jurisdiction over shoreline exemption issues when the issues are raised as part
of a permit appeal. However, in this case, the question of whether this project
was exempt from shoreline permit requirements because it constituted �normal
maintenance and repair� raised issues of fact that could not be determined on
summary judgment. The shoreline exemption issue was ultimately dropped. The
Board also considered and agreed with the appellants, that the Board lacked
jurisdiction to determine whether Northwest Aggregates could continue to use
and operate the barge-loading dock without a shoreline conditional use permit.
One major issue under contention in the
summary judgment was whether the project was a water dependent use. King County
had concluded it was not water dependent, and therefore that it was ineligible
for a shoreline substantial development permit (�SDP�) and a conditional use
permit (�CUP�) in the conservancy environment in which it was located. In
considering this question, the Board first determined that the principal use at
issue was the project as a whole, consisting of the sand and gravel operation,
including the mine and proposed conveyor and barge loading dock. Based on this
analysis, it went on to conclude the principal use was water dependent. The Board
also considered and rejected appellants� argument that the project was a
prohibited industrial or commercial use under the King County Shoreline Master
Program. Instead, the Board agreed with King County
that based on provisions in its own code, the use as a sand
and gravel mine was a resource use. The decision also included consideration of
King County�s Comprehensive Plan designations
for the site. Following statutory construction principles, the Board determined
that the provisions of the SMA and King County SMP should be harmonized with GMA
Plan designations if possible. Following the dismissal of some, but not all of
the issues on summary judgment, the case went to a nine-day hearing. The Board
concluded, in its final decision, that the SEPA review of the project had been
adequate, and that the proposal would not have adverse environmental impacts in
violation of SEPA or the SMA. Absent additional conditions, however, the
project as proposed could be inconsistent with King County Shoreline Master
Program and SMA requirements relating to recreation, noise, and the existing
character of the shoreline. Consequently, the Board established conditions for
operation of the barge loading dock, including limiting the hours of operation,
and modifications to existing monitoring plans. The Board reversed King
County�s denial of the permits and remanded the matter to King County for
issuance of a shoreline substantial development permit and shoreline
conditional use permit with conditions consistent with the Board�s order. The
Board�s decision is currently on appeal to King County Superior Court.
Wallingford Community Council v. City
of Seattle et al., SHB 04-012, Summary Judgment, Findings of Fact, Conclusions
of Law, Order (January 24, 2005).
This case involves issuance of an SPD to
convert a major vessel repair yard on Lake Union
to a dry boat storage and launch facility. The Board
decided several of the 15 issues identified in the case on summary judgment. The
Board ruled it did not have jurisdiction over an issue regarding ownership of a
portion of a right-of-way, and dismissed this issue. The Board also concluded
that Wallingford Community Council (�WCC�) had not met its burden of proof, or
established a material factual issue for trial, regarding compliance with the
SMA, state shoreline regulations, and relevant shoreline master program
provisions with the exception of: (1) whether parking should be allowed within
50 feet of the water�s edge; (2) whether the 35-foot height limitation applies
only to structures; and (3) the issues pertaining to view impairment under the
shoreline laws and substantive SEPA provisions. The Board reserved these issues
for hearing, and granted summary judgment on all other issues pertaining to
compliance with applicable shoreline laws. Finally, the Board concluded that
WCC had failed to meet its burden of proof or establish any material factual
issues for hearing on any of the procedural SEPA issues because WCC was unable
to prove the City�s threshold determination of nonsignificance
was clearly erroneous. Therefore, the Board granted summary judgment on all
SEPA procedural issues.
At hearing on the remaining factual issues,
the Board concluded that the project did not violate the view protection requirements
provided under the SMA, the Seattle Shoreline Master Program, or the SEPA
provisions. The Board was split on the height issue. Three members of the Board
found that the proposed project did not exceed the 35-foot height limit
established for the Urban Maritime Environment. They reasoned that the limit is
applicable only to the boat storage rack structures and not the additional height
attributable to vessels contained within the boat storage racks.
The other three Board members disagreed
with this interpretation and found that the proposed project violated the
35-foot height restriction. They concluded that the Shoreline Master Program
and SMA have the purpose of regulating developments and uses on shorelines and that
these laws are not limited only to structures. Because four members of the
Board were unable to agree on the height issue, the City�s decision stands
based upon operation of WAC 461-08-555(1). The Board also found that the alternative
parking arrangement submitted during the hearing by the project applicants
moved all of the parking spaces more than 50 feet outside of the water�s edge,
and therefore complied with the setback requirement, thus resolving this issue
in favor of the City. The Board�s decision is currently on review in King
County Superior Court.
Ed
Strickland v. City of Seattle,
SHB 04-011, Summary Judgment (December 23, 2004).
Strickland had applied to the City for a
shoreline substantial development permit (�SDP�) to reconfigure an existing
marina pier at Northlake Marine Works on Lake Union.
The reconfiguration, as proposed, would have resulted in an increase in overwater coverage of 216 square feet. The City approved
the SDP with conditions which prohibited an increase in overwater
coverage in the vicinity of the proposal, and which prohibited parking on the pier.
Strickland challenged the conditions.
The City moved for summary judgment,
arguing that as a matter of law it had the authority to prohibit an increase in
overwater coverage under its Shoreline Master Program
and its SEPA policies. Neither party contested the fact that Chinook salmon inhabit Lake Union, that Lake Union
is a migration route for Chinook salmonids, and that Chinook
salmon are listed as a threatened species under the Endangered Species Act. The
Board concluded as a matter of law, based on these uncontested facts, that the City
had authority under either its Shoreline Master Program or SEPA to prohibit an
increase in overwater coverage. The Board also concluded that the City had
the authority to prohibit overwater parking under its
shoreline master code, and dismissed the appeal.
C.F.
and Betty McNeal et al. v. Douglas County, Washington State Parks and
Recreation Commission, Washington State Department of Transportation, and PUD No.
1 of Chelan County, SHB 04-002, Summary Judgment (November 17, 2004), Findings
of Fact, Conclusions of Law, Order (March 4, 2005).
This appeal was brought by owners of
orchards in the Baker Flats area of Douglas
County, north of East
Wenatchee. The Washington
State Parks and Recreation Commission
(�Parks�) proposed the Rocky Reach Trail to run from East Wenatchee north along
the Columbia River to Rocky Reach Dam. The
trail would be located mainly in a public right of way acquired by Washington
State Department of Transportation (�WSDOT�) in the 1950s for highway purposes.
Parts of the proposed trail location are within shoreline jurisdiction. Over
the last few decades, the WSDOT right of way has been leased to the orchardists who grow a variety of tree fruits.
The permitting and environmental review
process occurred over a number of years. Parks identified the proposed trail as
a recreational trail in the beginning of the permit process. In addition to a
shoreline permit, Parks initially identified a Douglas County
recreational zoning overlay and zoning conditional use permit as required permitting
processes for trail approval. WSDOT disagreed with the identification of the
trail as recreational and with the use of a WSDOT right-of-way for recreational
purposes. Thus, the project was described as a multi-modal transportation use, including
recreational uses, that was related to the nearby by Highway 2/97
transportation corridor. The only local approval sought for the trail was the
shoreline permit.
The McNeals and
other orchardists appealed a number of issues,
including the underlying authority of Parks and WSDOT to pursue the project,
the impacts of the trail on agricultural properties, adequacy of SEPA review,
and whether the project complied with the SMA, the shoreline master program and
comprehensive plan. On summary judgment, the Board resolved a number of appeal
issues, determining that it did not have jurisdiction over compliance with land
use laws not incorporated into the local shoreline master program, whether
Parks or WSDOT had authority to pursue or fund the project, that no shoreline
conditional use permit was required, and that the trail was not prohibited by
previous Board decisions concerning the same WSDOT right-of-way.
After a two-day hearing, the Board
determined that the proposed trail complied with the Douglas County Shoreline
Master Program and the SMA, that the trail was compatible with surrounding
agricultural land uses, and that SEPA review was adequate. Related land use
appeals of the proposed trail are before the Douglas County Superior Court in a
LUPA appeal.