April 2004
The following
summarizes some of the cases decided in the winter and early spring 2004 by the
various boards that make up the state�s Environmental Hearings Office, in
particular the Shorelines Hearings Board (SHB) and the Pollution Control Hearings
Board (PCHB). This summary was prepared
by Bill Clarke, a member of the Pollution Control Hearings Board and Shoreline
Hearing Board, and Kay Brown, Administrative Appeals Judge for the Boards.
Environmental & Land Use
Law April 2004
I. Pollution Control Hearings
Board
A. PCHB Authority
Columbia River Alliance for
Nurturing the Environment (�CRANE�) v. Department of Ecology, PCHB 03-095, Temporary
Restraining Order (August 14, 2003), Order on Motion to Stay (August 26, 2003).
The Board issued a temporary
restraining order (�TRO�) under Civil Rule 65 prior to deciding whether to
grant a stay under its statutory
stay. In CRANE, appellants challenged (1) an Ecology concurrence with
the U.S. Army Corps of Engineers� (�Corps�) determination that the Corps�proposed Columbia River Channel Deepening Project is consistent
with the Washington Coastal Zone Management Plan, and (2) an order from Ecology
certifying that the project complies with Washington�s water quality standards. The
Board issued a temporary restraining order based on the test from Tyler Pipe
Indus. v. Department of Revenue, 96 Wn.2d 785, 792 (1985).
After the TRO was issued, CRANE
then moved for a stay under the Board�s stay statute, RCW 43.21B.310. CRANE
sought to stay Ecology�s decision so that review by the Board would occur prior
to the issuance of a Record of Decision by the Corps on the project. The Board
ruled that CRANE was entitled to the stay to allow such review at the state
level to occur before the Corps issued its final decision. The Board also
accelerated the schedule for review of the case in light of Airport
Communities Coalition v. U.S. Army Corps of Engineers and Port of Seattle,
280 F.Supp.2d 1207, 1218 (W.D. Wash. 2003), in which Judge Rothstein ruled that
in a Clean Water Act � 401 certification the Corps need only include conditions
imposed by the state, including both Ecology and on judicial review, within a
year of issuing the notice for request for certification. After the stay was
issued, the CRANE appeal settled.
B. Water Rights
Familigia LLC v. Department of Ecology, PCHB 03-072, Summary Judgment
(October 31, 2003), Order on Reconsideration (January 30, 2004). In this case, Familigia LLC sought to adjust groundwater rights approved
for primarily irrigation use, with a minor component for recreational and
domestic supply, to allow for increased domestic use to support development of
a hotel complex and small vineyard. A portion of the water rights were
inchoate. Ecology denied the change of use under RCW 90.44.100 on the basis
that the groundwater transfer statute does not allow changes in purpose of use
for inchoate groundwater rights, only changes in the �manner of use. Ecology
also denied the water rights changes under the Family Farm Act (�FFWA�).
The PCHB first considered the
meaning of the phrase �manner of use� in RCW 90.44.100, the groundwater change statute.�
Before the Board, Familigia argued that within the
groundwater code �manner of use� is synonymous with �purpose of use.� Ecology
argued that the Supreme Court had resolved the matter in R.D. Merrill v.
PCHB, 137 Wn.2d 118 (1999). Familigia countered
that the Supreme Court�s consideration of the phrase �manner of purpose� in RCW
90.44.100 was only dicta, because the manner of use of the two unperfected groundwater
rights were not at issue in the Merrill decision.
On summary judgment, the Board
ruled for Ecology, finding that RCW 90.44.100 did not allow for changes in the purpose
of use of unperfected groundwater rights, relying on the Supreme Court�s decision
in Merrill. On a motion for reconsideration by Familigia,
the Board reversed its decision, finding that �manner of use� and �purpose of
use� were synonymous, and that the issue was not squarely before the Merrill
court. The initial majority and dissenting Familigia
LLC opinions essentially changed places, and were supplemented with new
opinions upon reconsideration.
The Board also reviewed
Ecology�s denial under the FFWA. Under the FFWA, a water right may be changed
to a different use if the use is within a designated urban growth area under
the Growth Management Act (�GMA�), or in non-GMA counties, in areas designated
for urban growth. RCW 90.66.065(2)(c). Familigia argued that the hotel complex for which the water
would be used was within an urban growth area because the project is a Master Planned
Resort under GMA. The Board ruled that while designation of a Master Planned
Resort may show that an area is urbanizing, it does not mean that the area has
been designated as an urban growth area.
Ecology also refused to approve
the water rights change under the lease provision of the FFWA, which states
that a FFWA water right may be changed to any purpose of use �if the transfer
is made exclusively under a lease agreement.� RCW 90.66.065(2)(b).
Familigia argued that this denial was premature,
because no lease was presented to Ecology for review. The Board ruled that even
though a particular lease was not at issue, that the project did not qualify
under the FFWA lease provision. In so deciding, the Board considered the
specific lease provision in light of the intent section of amendments to the
FFWA in 2001 legislation. The Board found that the legislation was intended to
allow �temporary leases [of] . . . family farm water permits.� Upon
reconsideration, the Board did not modify its decision that the proposed change
did not meet the lease provisions of the FFWA, though it reinforced the need
for legislative clarification of the FFWA lease provisions, and the concurrence
recognized that there was no lease before Ecology.
Port of Vancouver, U.S.A. v.
Department of Ecology and Clark Public Utilities, PCHB 03-149/151, Order
Granting Stay (November 26, 2003). The PCHB considered the
application requirements for a preliminary water right permit and the
applicability of SEPA to such a permit. The Board reviewed these issues in the
context of a motion for stay of a preliminary permit, and will review the
merits of this permit appeal in 2004. Clark Public Utilities (�CPU�) is seeking
to develop a new groundwater supply in the Vancouver Lake
lowlands area. As part of this new supply, it submitted a water right permit
application to Ecology. The Vancouver
Lake lowlands area has
been the site of industrial activities over the past century that has resulted
in groundwater contamination. Port
of Vancouver and other
appellants are some of the parties currently working to contain and clean up contaminated
groundwater. These same parties appealed a preliminary permit issued to CPU to
test a well at one of the potential wellfield
locations, on the basis (1)� that there was no water right application
corresponding to that well depth and location and (2)� that SEPA review of the wellfield project had not occurred.
The Board applied RCW 43.21B.320(3), the Board�s statutory stay test. The Board
found that appellants did not meet the �likelihood of success� requirement for
a stay based on its claims that CPU�s application for a groundwater right was
insufficient to support issuance of preliminary permit. The Board ruled that
under RCW 90.03.290(2), �Ecology has the undisputed statutory right to issue
preliminary permits . . . .�
However, as to the claim that
the preliminary permit should not be issued prior to a SEPA threshold
determination, the Board found that appellants met the �likelihood of success
on the merits� test for issuance of a stay. Thus, a stay would be issued unless
CPU or Ecology could show both a likelihood of success and an overriding public
interest why the stay should not be issued. The Board determined that neither
CPU nor Ecology made such a showing, and thus issued a stay of the preliminary
permit. A decision on the merits of the case is expected in 2004.
Confederated Tribes and Bands
of the Yakama Nation v. Department of Ecology, PCHB 03-030, Summary Judgment
(October 31, 2003).
In an appeal brought by the
Confederated Tribes and Bands of the Yakama Nation, Nez Perce Tribe, and
Confederated Tribes of the Umatilla Indian Reservation (�Tribes�), the Tribes
challenged five (5) water permits issued by Ecology for surface water right
diversions from the Columbia River. Four of
the five were issued to irrigation districts and a hospital district for
irrigation. The fifth was issued to Mercer Ranches for industrial food
processing. The total water approved to be withdrawn from the Columbia
River under the permits was approximately 138 cubic feet per second.
Tribal
Consultation. The
Board granted summary judgment to the Tribes because they were not consulted prior
to the issuance of the permits. Consultation with the Tribes is required by
Ecology rules. See WAC 173-531A-060 and WAC 173-563-030(4).
The Board concluded that the rules require Ecology to engage in a �meaningful, continuing
consultation� with the appropriate Indian tribes. The Board opined that
consultation did not require negotiation, but it did require �more than a
letter of notice of the possibility of consultation.� Although Ecology may have
had some contact with the Tribes at an early stage in the processing, when
Ecology made a substantial change to its proposed decision it was necessary to
consult with and seek the advice and evaluation of the Tribes. On this basis, the
Board remanded all five applications back to Ecology for proper consultation
with the Tribes prior to issuing a final decision on the applications.
SEPA
Exemption. Although
remanding the applications to Ecology, the Board addressed the remaining issues
which were the subject of pending motions in order to provide guidance to the
parties should the case return to the Board. One issue concerned Ecology�s lack
of SEPA process when it issued the water right permit to the Kennewick Public
Hospital District (�KPHD�). The Tribes argued that the application should have
been subject to SEPA despite qualifying for a SEPA exemption. They based this argument
on WAC 197-11-305, a SEPA rule that �unexempts�
actions exempt under Part Nine of the SEPA rules because they are a segment of
the same proposal as other pending actions. The Board concluded that the KPHD application
was not part of the same proposal as the other applications because it was made
by a different entity. Therefore, the
Board ruled that Ecology was correct in concluding the KPHD permit remained
exempt from SEPA.
Standing
and Impairment. The
Tribes moved for summary judgment on the issue of whether Ecology had failed to
adequately consider impairment of existing rights when it issued the permits.
Ecology responded that the Tribes did not have standing to argue this issue.
The Board disagreed, citing the Tribes� valuable treaty rights to fish on the
Columbia-Snake River system as establishing their standing to assert the 1980
minimum flows contained in WAC 173-563. However, the Board concluded there were
genuine issues of material fact regarding the substance of impairment,
and therefore the impairment issue should proceed to trial.
Other
Issues. The
Board also concluded that the issue of cumulative impacts of the five
applications was a contested issue of fact for trial. Finally, the Board opined
that Ecology did not improperly grant a change to KPHD�s
water permit when it approved the permit for a lower amount of water withdrawal
than was originally applied for. The Board said the Tribes� argument was based
on the faulty premise that KPHD had an initial water permit for a higher amount
of water. In fact, all the KPHD had was a pending
application, which was amended. This did not constitute a change to a water
right. The Board�s decision was appealed to Benton County Superior Court in
November 2003.
II. Forest Practices Appeals Board
Lummi Island Land Co. v.
Department of Natural Resources, FPAB 00-013, Summary Judgment (September
11, 2003).
In Lummi Island Land Co., the
Forest Practices Appeals Board addressed the issue of automatic approval of
applications under RCW 76.09.050. The applicant submitted its application on
March 17, 2000, the last day before the effective date of the new temporary
rule changes implementing the forest and fish agreement. The application proposed
two harvest units, each involving removal of fifty percent of the merchantable
timber from 110 acres and 125 acres respectively. The application did not
contain any specific disclosure about steep slopes on the property or any
geologic assessment of the harvest area, nor did it contain sufficient
information to fully evaluate the proposal�s impact on peregrine falcons in the
area. DNR initially classified the application as a Class III forest practice.
After receipt of the
application, DNR requested additional information. When the information was
provided on March 28, 2000, it included maps that contained some conflicting
information. More information was requested, and eventually the applicant
submitted a geotechnical report. The applicant also indicated it would be
reducing the 125-acre harvest unit to 32 acres. On April 21, 2000, DNR gave the
applicant verbal notice that its application was being denied. Written notice
of denial was provided on April 27, 2000.
The issue before the FPAB was
whether the application was automatically approved 30 days after the date it was
submitted, which would have been April 17, 2000. DNR argued, and the Board
agreed, that the timeframe for approval under RCW 76.09.050 did not start until
a complete application was submitted. It based its decision on WAC
222-20-010(7), which provides that applications are not considered received
until they are complete. The Board opined that it did not have jurisdiction to
consider the validity of this rule, but must apply it to the facts of the case.
The Board concluded the application was not complete until all the information
necessary to review the application had been submitted. In this case, that was
at least March 28, when additional detailed maps and information were
submitted. Further, the Board reasoned even if the application was considered complete
when first submitted, and therefore deemed approved by operation of law on
April 17, 2000, the applicant would have needed to submit a new application on
April 21, 2000, when the size of the harvest was reduced by 75 percent. It
concluded that this change was substantial, thus triggering the requirement for
a new application contained in RCW 76.09.060(5).
III. Shorelines Hearings Board
A. SHB Jurisdiction
McArthur v. City of Long Beach and Pacific
County, SHB 03-017, Summary Judgment
(October 28, 2003).
The McArthurs
challenged Pacific
County�s approval of a
shoreline substantial development permit (�SDP�) for construction of the Seaview Dunes segment of the Discovery Trail. Their general
contention was the public would further destroy the dunes if the trail were
built. The SHB granted summary judgment to the City and the County, and upheld
the issuance of the SDP.
The McArthurs
made several specific arguments as to why the County�s approval was not valid.
First, they argued the City of Long
Beach did not actually own the property, or that its
ownership was subject to deed restrictions. The Board rejected the City�s
argument that the petitioners lacked standing to raise this issue. The Board noted
that the McArthurs would be injured if the permit were
illegally granted to someone who does not have legal possession of the
property, because they live adjacent to, and have had a portion of their
property condemned for, the trail. The Board went on to conclude, however, that
it did not have jurisdiction to rule on any alleged violations of deed
restrictions.
Also in McArthur,
appellants argued the proposed project did not involve a statewide interest as
required by the Shoreline Management Act. The Board rejected this argument. It
concluded even if a majority of the users of the Seaview
Dunes segment of the trail were local, the trail as a whole celebrates a
statewide and national event, the Lewis and Clark expedition. The McArthurs also contended the project was short-term,
because the trail was being constructed as part of a bicentennial
commemoration. The Board concluded the trail project would likely long outlive
the bicentennial commemoration, and would be a permanent memorial to the Lewis
and Clark expedition on the Washington
Coast. April 2004 Environmental &
Land Use Law
The McArthurs
also contended the construction of the trail would increase illegal use of the
dunes by four-wheel drive vehicles and would cause damage to the resources and
ecology of the shoreline. The Board rejected this argument. The Board
concluded, based on the photographic evidence submitted of the existing trail,
plus the opinions of the experts at Ecology and State Parks, that construction of
the Seaview Dunes segment of the trail would help improve
the character of the dune environment by focusing recreational activity into
one corridor. The Board also noted that the petitioners, who had the burden of
proof in the appeal, had offered no contrary expert opinion on this question.
Additionally, the McArthurs argued the trail segment constituted a commercial
development. The Board rejected this argument, noting that there was no mention
of any fees for use of the trail by the public, nor was there any mention of
promoting trade or commerce. Finally, the McArthurs
argued that only low-intensity recreational uses are permitted within
conservancy shoreline environments,mand
then only if they do not change or detract from the character of the
environment. The Board concluded that the trail use would meet these
requirements, and was consistent with the master plan. It noted that the trail
use would be primarily pedestrian, bicycle, and wheel chair oriented, and would
be non-polluting.
Washington State
Ferries v. City of Edmonds
and Department of Ecology, SHB 03-013, Summary
Judgment (October 28, 2003).
The Board ruled that a
discretionary appeal before a local government need not be filed before filing
an appeal of a shoreline permit decision with the Shorelines Hearings Board.
The City of Edmonds issued Washington State Ferries (�WSF�) a temporary
shoreline permit for an overhead loading facility at the Edmonds ferry
terminal, even though WSF sought a permanent approval. WSF appealed to the SHB
without filing an appeal with the Edmonds City Council. The Board ruled that
because the City Council appeal was discretionary, WSF need not appeal to the
City Council prior to its SHB appeal.
The Board also ruled that the
ferry terminal project must be consistent with local comprehensive plans and development
regulations, as well as the SMA and local Shoreline Master Program. Applying
these laws, the Board ruled that the City�s approval of a temporary shoreline permit,
rather than a permanent approval, is not precluding the siting
of a ferry terminal, but approving the continued temporary location of the
overhead loading facility. The Board
dismissed WSF�s appeal on the basis that the approval
by the City was consistent with applicable state and local laws.
B. Effect of Prior Permits
Yale Estates Homeowners
Association v. Cowlitz
County, SHB 03-012, Summary Judgment
(December 22, 2003).
The Board determined that
conditions in a prior shoreline permit could act as a legal bar in a future
shoreline permit application. In this case, the Board reviewed the County�s
denial of a shoreline substantial development application from lot owners
seeking to construct a number of private recreational docks. The County based
its denial on the conditions in a shoreline permit issued to owners of the same
lots in 1995. In the 1995 permit approval, the lot owners were allowed to
substantially modify the lakeshore for purposes of shoreline stabilization. As
part of that permit review, the County reviewed shoreline access issues, including
the construction of docks, and included a permit condition that prevented the
lot owners from building docks. The County permit stated that boating access should
occur through use of a nearby public access launch.
The Board held that the dock
prohibitions in the 1995 permit acted to bar the construction of docks from a
new permit. The Board relied on Hilltop Terrace Ass�n
v. Island County, 126 Wn.2d 22, 33 (1995) for the proposition that a shoreline
use or development that was specifically prohibited in a prior permit may not
be later challenged, unless the original permit itself has been vacated or
abandoned, or unless there has been a substantial change in circumstances or
conditions relating to the prohibition. The Board found that the dock
prohibition was within the scope of the permit sought by the lot owners at that
time, and that the dock prohibition was never appealed.
C. Ordinary High Water Mark
Stafford v. City of Bainbridge Island et al.,
SHB
03-010, Findings of Fact, Conclusions of Law, Order (October 31, 2003).
The SHB considered the
interesting issue of whether an exemption from a shoreline development
requirement may alter the location of the ordinary high water mark (�OHWM�).
The Board addressed this question in the context of property owned by the Staffords on Point Monroe Sand Spit on Bainbridge Island.
In 1990, a major storm hit the area causing damage to homes and bulkheads. Emergency
repairs were authorized, and the Stafford�s bulkhead
was built pursuant to a shoreline exemption.
In 1997, the Staffords decided to build a
single-family residence on their property. This project required a shoreline variance.
To obtain a variance, it was first necessary to determine the location of the
OHWM. RCW 90.58.030(2)(b) identifies three methods by
which the OHWM may be determined: (1)� by ascertaining the vegetation line,
(2)� by ascertaining where the OWHM has been changed by permits, or (3)� by
relying, in the case of saltwater, on the �mean higher high tide.� The Board
concluded that it was not possible to determine the historic OWHM by the
vegetation line because of the major storm and the existence of bulkheads. The
Board then concluded that reference could be made to the tidal datum line.
Further, the Board opined, the
second method of determination of the OHWM could also be used. The Board concluded
that the historic OHWM in this case had been altered due to the construction of
the bulkhead pursuant to a shoreline exemption. A majority of the Board was
persuaded RCW 90.58.030 allows an exemption decision, as well as an affirmative
decision on a permit, to change the OHWM. The Board concluded that the key was
whether the shoreline exemption received actual review by the local government.
If so, the granting of an exemption is a substantive granting of �permission�
authorizing the activity involved. Here, the Board was persuaded that the Stafford�s exemption for its bulkhead had received actual
review, and therefore did have the effect of changing the OHWM. The Board
dissent did not agree that the OHWM could be changed by a permit exemption.
Further, the dissent thought the historic OWHM in this case could be
ascertained by reference to the vegetation line.
Based on its determination of
the OHWM, the majority went on to address the requirements for granting of a variance.
The Board concluded that all were met except for the requirement a variance be
the minimum necessary to afford relief. The Board was not convinced the
proposed structure was the minimum necessary. On this basis it remanded the
variance application back to the City with leave to amend the application to comply
with the �minimum necessary variance criteria.� The Board�s decision is
currently on appeal in Thurston County Superior Court.
D. SEPA Review
Department of Natural Resources
v. Kitsap County, SHB 03-018, Summary Judgment
(December 16, 2003).
This case was an appeal by DNR,
with an intervention by the Department of Fish and Wildlife, of Kitsap County�s
denial of shoreline permit for geoduck harvest in Kitsap County.
Kitsap County denied the permit application on the
basis that SEPA review of the proposed geoduck
harvest was insufficient, and raised a variety of SEPA issues in the appeal.
In response to motions for
summary judgment, the Board first ruled Kitsap
County was not collaterally estopped from challenging DNR�s
reliance on its own programmatic EIS by a 1992 SHB decision on geoduck harvest in Kitsap County
that included similar SEPA issues. While the issues were similar, the prior Kitsap County
geoduck SHB appeal concerned different SEPA documents
and permit applications than those at issue in the present appeal. Thus, the
first test needed to apply the doctrine of collateral estoppel,
(�the issue in both actions is identical�) was not met, and thus collateral estoppel could not apply. Ecology v. Yakima Reservation
Irrigation Dist., 121 Wn.2d 257, 296 (1993).
On remaining SEPA claims,
however, the Board ruled in favor of DNR. The Board ruled against Kitsap County
that simply because DNR was both the project proponent and SEPA lead agency, it
does not create a conflict of interest that justifies and/or authorizes Kitsap County
to require DNR to pay for an independent expert to review its SEIS. The Board
found that DNR had appropriately separated its SEPA review responsibility from
its project permitting activity.
The Board also ruled that Kitsap County
could not use the shoreline permit appeal as a collateral attack on the SEPA
SEIS, which had a separate appeal process that had already lapsed. Finally, the
Board ruled that under WAC 197-11-545, Kitsap County
could not raise the SEPA issue of lack of independent review at this time,
because the County had not properly raised those issues in its comments to the
drafts of the SEIS. Finally, the Board found that DNR�s
SEIS, prepared for a non-project action, and supplemented by individual
Environmental Assessment of proposed geoduck harvest
tracts, was adequate under SEPA and the SEPA Rules, Chapter 197-11 WAC, as a project
specific EIS.