The following notes summarize selected cases
heard by various Boards of the Environmental Hearings Office. The cases represent the following
important issues heard by the office:
Standing (Water Rights); Res Judicata (Water Rights); Statutory
Construction (Water Rights); Self-incrimination; National Pollutant Discharge
Elimination System (NPDES) Public Notice and Information; Permit Enforcement
(Forest Practices); Finality and City Codes (SEPA and SMA); Shoreline Variance
and SMA Rule-making. These issues are
discussed below.
WATER RIGHTS
The Pollution Control Hearings Board
(PCHB) was asked to address the issues of standing, res judicata and statutory
construction in various water rights appeals.
STANDING
Ironworkers
Local 29 v. Ecology, PCHB NO. 01-007 presented the Board with the problem
of determining whether a union organization, an individual citizen and a public
interest group had standing to appeal Ecology�s approval of the City of
Goldendale's water rights change application.
The City of Goldendale applied for
the change of five water rights in October of 2000 due, in part, to a �boil
water� advisory from the Department of Health.
Although Ecology did not grant the quantity of water right sought by the
city, it did approve water rights in a reduced quantity (479.2 acre feet
instead of 1,134). These rights were
changed from an �agricultural� purpose to �municipal-industrial� one. The essence of the challenge from the
citizen groups was the change in use.
They opposed the change in use and thought this, combined with the
quantity changes, would have a detrimental effect on the watershed.
The PCHB granted the motion to
dismiss for lack of standing. The PCHB
determined the citizen groups did not meet the three-part test for standing
under Core v. Olympia, 33 Wn. App.
667, 567 P.2d 790 (1983). The PCHB
held they did not show: 1) an injury in fact, 2) that falls within the zone of
interests protected by the statute at issue, and 3) redress-ability. Appellants have petitioned for Superior
Court review.
RES JUDICATA
The
PCHB ruled on whether failure to appeal a prior order was res judicata in Lake Entiat Lodge v. Ecology, PCHB NO.
01-025. The merits of this case
presented, for the first time, the problem of quantifying water rights using
the �pumps and pipes� method invalidated in Department
of Ecology v. Theodoratus, 135 Wn.2d 582, 957 P.2d 1241 (1998). The original water right application the
Lodge operated under was submitted in 1968.
Construction delays resulted in the Department issuing five �due
diligence� extensions between 1969 and 1976.
However, a water right certificate was issued in 1977 at 160 gallons per
minute (gpm) and 256 acre feet based on the capacity of the pump and the piping
system.
In
1998, because of water quality problems and health issues, the Lodge
constructed new wells and applied for a change to their ground water
certificate to add the new point of withdrawal. Ecology approved the change in withdrawal in an expedited
decision. Yet, included in the �decision
and order,� in an attempt to conform to Theodoratus,
was a �recommendation� to rescind the prior ground water certificate and
replace it with a superseding permit.
The Lodge failed to appeal this decision, which Ecology implemented two
years later. After this implementation,
the Lodge appealed.
The
Board issued a split decision. One
Board member, in determining the decision was not �final,� sought to reach the
merits of the Theodoratus problem.
The other Board member determined the failure to appeal to be res
judicata. However, when there is a
split decision, per Department of Ecology
v. City of Kirkland, 84 Wn.2d 25, 30-31, 523 P.2d 937 (1974), the result is
Ecology's original determination is upheld.
STATUTORY CONSTRUCTION
The PCHB was asked to interpret the
�stockwatering� exemption in RCW 90.44.050 in Devries v. Ecology, PCHB 01-073.
Devries opened a new dairy in Yakima County with 2,261 cows. It was estimated the herd consumed between
39,000 and 56,000 gallons of water per day (gpd). Water was supplied from five wells and was used for human and
animal drinking and other subsidiary purposes, which included for example,
cleaning milking equipment. When the
herd reaches full strength (4,400 cows) the estimate for water consumption was
in excess of 110,000 gpd. Ecology
issued a compliance order requiring the dairy to cease using groundwater in
excess of 5,000 gpd.
At
issue was whether the stockwatering exemption to the groundwater permitting
requirement was unlimited or limited to 5,000 gpd; whether all authorized uses
under the exemption are limited to 5,000 gpd or whether each discrete use has a
limit of 5,000 gpd; whether the term "stockwatering" includes the
consumption of water for dairy cows; whether the term "stockwatering"
includes water for the various subsidiary functions to operate a dairy farm;
and whether the term "industrial" as a purpose contains the
subsidiary functions necessary to operate a dairy farm.
In
its Summary Judgment decision, the PCHB ruled that proper statutory
construction required reading the entire section as a whole � including each
proviso. It held the exemption was
limited to 5,000 gpd. It held the various uses should not be separated for
calculation of the quantity limit. It
concluded the term �stockwatering� included water for a commercial dairy
operation and its subsidiary functions.
However, the Board ruled the term �industrial� did not include the
operation of a dairy farm. Ecology�s
compliance order was affirmed. The
parties have appealed this decision to Superior Court.
WATER
QUALITY
Three
important issues arose in water quality cases before the PCHB. One unusual matter focused on constitutional
protections against self-incrimination.
Another related directly to water quality standards in issuing National
Pollutant Discharge Elimination System (NPDES) General Permits. The third case addressed the issue of public
notice and participation in the issuance of a NPDES permit modification.
SELF-INCRIMINATION
In
Jerome Rosa d/b/a Jer-Rosa Dairy v.
Ecology, PCHB No. 01-083, the appellant, Mr. Rosa asserted that proceeding
with the hearing on his civil penalty appeal would threaten his Fifth Amendment
protections against self-incrimination.
Citizen
complaints about a discharge from a manure lagoon into the South Fork of the
Chehalis River, led to an inspection of Jer-Rosa Dairy and the subsequent
penalty. Ecology also began a criminal
investigation into this activity. The
two Department actions led Mr. Rosa to conclude that he was at risk. Upon appealing his civil penalty to the
PCHB, Mr. Rosa moved to stay the proceedings until resolution of the criminal
matter.
The
PCHB denied the motion for stay. The
Board relied on King v. Olympic Pipeline
Company, 104 Wn. App. 338 (2000), review denied 143 Wn.2d 1012 (2001). In King,
the Court's self-incrimination analysis required the trial court to balance, on
the record, the competing interests involved.
The Court framed this balancing exercise in the form of a multiple
factor test. In ruling on Mr. Rosa�s
motion, the analysis of the PCHB followed the multiple factor test in King.
Mr. Rosa appealed the denial to Lewis County Superior Court, which
upheld the Board�s analysis and decision.
WATER
QUALITY STANDARDS
Puget Soundkeeper Alliance v. Ecology,
PCHB NO. 00-173 directly dealt with water quality standards. Puget Soundkeeper Alliance (Soundkeepers)
and various other parties asked the PCHB to stay extension of coverage under
two General Permits: one for Stormwater Discharge Associated with Construction
Activities (Construction Stormwater Permit or �CSWP�) and one for Stormwater
Discharge Associated with Industrial Activities (Industrial Stormwater Permit
or �ISWP�). In its implementation of
the Federal Clean Water Act (CWA), Ecology issues general permits as an
alternative to issuing individual NPDES discharge permits.
Soundkeepers
argued that coverage should not be extended under the CSWP or ISWP to any
discharge that would add an identified pollutant to waters listed under �303
(d) of the CWA. Ecology argued that
general permit coverage was appropriate in the absence of an established Total
Maximum Daily Load (TMDL) for pollutants.
The
PCHB conditionally granted Soundkeepers� motion for stay for the Construction
Stormwater Permit and the Industrial Stormwater Permit. The Board found that the CWA prohibits
permits for discharges that exceed water quality standards. In so ruling the Board adopted the following
permit conditions: 1) New discharges to
�303(d) listed waters will not be allowed coverage if the anticipated discharge
will include the pollutant for which the water body is listed unless it can be
documented that no water quality violation will occur, and 2) New discharges to
a water body for which a TMDL has been developed will not be allowed coverage
unless the discharge would be in compliance with the TMDL.
PUBLIC
NOTICE AND INFORMATION
Citizens Against SeaTac Expansion v.
Ecology and the Port of Seattle, PCHB N0. 01-090
brought before the PCHB the important issue of the scope of public notice and
information required on an NPDES permit modification.
The
Port moved for dismissal and the Citizens Against SeaTac Expansion (CASE) moved
for partial summary judgment. The Board
treated both as motions for summary judgment.
On CASE�s motion for summary judgment the issues were: 1) whether � 401
certification was a pre-condition to NPDES permit modification; and 2) whether
Ecology�s public participation process was consistent with applicable law in
relation to the permit, the fact sheet and public notice.
The
PCHB ruled against CASE on every summary judgment issue but one. The Board agreed with CASE in finding that
the Fact Sheet addendum did not provide sufficient information. CASE had argued that the Fact Sheet addendum
was inadequate because it failed to identify points of discharge by sketch or
description. 40 CFR 124.56; WAC
173-220-060. The Board found that
although federal regulations provide discretion to the agency in requiring
compliance with this provision, state regulations do not. State regulations describe these elements as
the �minimum.� The Board stated that:
�Fact sheets are an important aspect of the
notice and information given to the public to allow it to actively participate
in the NPDES decision-making process. Adequate information, especially something as critical as a point
of discharge, cannot be overlooked, eliminated, or provided in an ad hoc or
after-the-fact manner. �
The
Board remanded the NPDES permit and Fact sheet to Ecology to correct the
deficiencies in the FACT sheet consistent with the opinion.
FOREST
PRACTICES
The
Forest Practices Appeals Board (FPAB) was presented with an appeal that raised
the issue of permit enforcement. Dukich v. DNR and Diversified Forest
Products, Inc. FPAB NO. 99-020 involved
an appeal from a Department of Natural Resources (DNR) approved Forest
Practices Application (permit) issued to Diversified Forest Products, Inc.
(DFPI). The permit allowed DFPI to
construct a 10 ft. wide, 1480 ft. long road to reach a cabin near Bead Lake in
Pend Oreille County. The permit
contained many conditions on the project including one for re-vegetation.
Dukich
originally appealed the permit, but a settlement agreement was reached that
gave Dukich a right to reactivate proceedings before the Board. The settlement agreement also provided that
"upon re-initiation of the proceedings in this appeal all rights and
duties of the parties under this stipulation will cease..."
Despite
this settlement, when the project neared completion trouble began. DNR, DFPI and the County felt the project
was complete. Dukich disputed this
because all conditions of the permit had not been met - among them
re-vegetation. DNR moved to dismiss
arguing that the matter was moot. The
Board denied the motion noting that under the settlement agreement the matter
was not "moot" since all conditions had not been met. However, Dukich subsequently exercised his
rights under the reactivation clause of the settlement agreement, thus ending
the rights and obligations of all parties under that agreement.
DNR
moved for summary judgment, again arguing that the appeal was moot. The Board granted DNR's motion. In its analysis the Board characterized the
issue as one of permit enforcement versus proper permit issuance. It noted that it did not have enforcement
jurisdiction and that such issues were properly submitted to superior court.
RCW 34.05.570(4). The particular
conundrum arose from proceedings that took place under the settlement
agreement. However, since the appellant
had reactivated the appeal the settlement agreement was no longer in
force. Accordingly, its definition of
mootness no longer governed and could no longer form a basis for the Board's
ruling. Even though the Board strongly
stated its disapproval of DNR's failure to enforce the terms of the permit, the
Board concluded that it did not have jurisdiction for the relief requested and
dismissed the appeal as moot.
SEPA/SHORELINE
MANAGEMENT ACT (SMA)
In
Luce and McFadden. v. City of Snoqualmie
and Northwest Railway Museum, SHB NO. 00-034 the Shorelines Hearings Board
(SHB) addressed the issue of whether a Shoreline Substantial Development Permit
(SDP) was sufficiently detailed or complete.
The
City of Snoqualmie issued the SDP and a Determination of Non-Significance (DNS)
to the Northwest Railway Museum (NRM).
These actions were taken in the course of NRM�s Phase 1 development of a
Railway Conservation and Restoration Center (CRC). The CRC was planned to help facilitate NRM�s 50-year mission of
operating the historic railroad and restoring its collection of railroad
artifacts and rolling stock. The
restoration involved working with hazardous materials (paints, lubricants,
greases, solvents, paint thinners and asbestos). Pre-application review by the city predicted that the project
would require five permits. NRM decided
against utilizing the city�s permit consolidation procedure. The city incorporated ten conditions into the
SDP. Many of the conditions referred
to the applicant�s need to �obtain� other city permits or �comply� with other
relevant regulations that required additional regulatory processing.
Nearby
property owners appealed the city�s actions to the Shorelines Hearings
Board. They claimed that city
issuance of the DNS violated SEPA and that the city failed to adequately
evaluate the impacts of the project on the environment and also the use of
hazardous materials.
The
SHB remanded the SDP and the DNS back to the City of Snoqualmie for �processing
and reconsideration.� The SHB found
that the SDP lacked completeness and contained �several major errors.� The
incomplete nature of the proposal left the Board with �no idea what was
approved� by the City. It lacked final
drawings and site plans. There was not
sufficient detail to enable the Board to determine if it complied with
SMA. It failed to delineate a
wetland. There was no clear indication
of the final approved plan. In
closing, the Board noted that the city relied too much on its code rather than
�specifically evaluating the impacts of the proposal on the environment,� in
violation of SEPA.
SHORELINE
VARIANCE
The
SHB had to answer the question whether an approved building permit could remain
valid if the applicant never picked it up in Jacobs v. San Juan County, SHB NO. 01-015.
The appellants applied to move a house to
their lot on the North end of San Juan Island.
The application indicated only two trees were to be cut. After permit review, a San Juan County
employee telephoned the appellants to notify them that their building permit
was ready for pick up. They were
advised to pay the fee at pick up.
Because of the presence of natural vegetation, the house was allowed to
be set back only 50 feet from the shoreline.
The
contractor's plan was to barge the house to the waterside of the lot and then
move it up the embankment to the agreed site.
Despite the early indications that only two trees would be cut and
minimal grading would occur, the contractor proceeded with extensive tree
cutting and grading. However, the work
began before the Appellants picked up the permit. This resulted in the issuance of Notices of Violation, Stop Work
Orders and penalties. With the tree
screen removed, the County indicated that the house needed to be moved back to
100 feet from the shoreline or that a shoreline variance was required. The appellants applied for the variance but
the hearing examiner denied the application and the County denied their appeal.
The
SHB reached a split decision, which resulted in upholding the county�s decision. The Board majority found that verbal
authorization did not cause the permit to issue. So the construction activity was unauthorized and the 100 ft.
setback in force. Therefore, the
majority determined that a variance was required. However, the majority decided that the appellants did not meet
the legal conditions for a variance.
Accordingly, the result was that the house had to be moved to the 100ft.
setback.
The dissent found requiring both compliance
with the 100ft. setback and restoration to be double punishment. They held that moving the house to the
100ft. setback was more injurious to the environment than letting it
remain. The dissent determined that
given the County's various errors in the process of regulating the house move,
it should exercise its discretion differently and authorize the house to remain
as sited.
SHORELINE
MANAGEMENT RULES APPEAL
Perhaps
the most important case of the year required the SHB to rule on the validity of
the new SMA Guidelines prepared by Ecology over the last five years. Association
of Washington Business v. Ecology, SHB NO. 00-037 was the culmination of
many years of public process and hard work by many individuals.
It
all began in 1995 when legislation was enacted requiring Ecology to update the
Shoreline Management Act (SMA) guidelines.
RCW 90.58.060(3). Originally
adopted in 1972, the current guidelines had never been updated. After review, Ecology determined that the
existing guidelines were inadequate to enforce the SMA. Ecology published the first draft of the
guideline revisions in 1999. Those
rules were withdrawn, reissued, and on November 29, 2000 became final. A multitude of public and private entities
appealed these rules to the SHB for review.
The
SHB issued its ruling on August 27, 2001.
Three members concurred in and dissented from the majority opinion.
Thus, the SHB review resulted in three written opinions: a majority opinion, a
concurrence/dissent by one member and a concurrence/dissent joined in by two
members.
The
Majority opinion decided that the Department of Ecology does not have express
or implied authority to implement the Endangered Species Act (ESA). It held that the ESA compliance requirements
in the Guidelines violate the Administrative
Procedures Act (APA) but that the Guidelines properly required
preservation and restoration of Property Functioning Conditions. The SHB also held that the Guidelines do
not improperly shift the balance of policies under SMA. However, the Board found the Guidelines
improperly regulate uses that are exempt under SMA by requiring letters of
exemption. The SHB held that the
Guidelines do not effectively prohibit gravel mining. The SHB held that Ecology violated requirements to prepare a
Small Business Economic Impact Statement (SBEIS), Implementation Plan and
Cost-Benefit Analysis. Finally, the
Board determined that Ecology did not improperly impose an unfunded mandate on
local government and that the Guidelines do not conflict with the Growth Management
Act (GMA). In its final order, the
Board remanded the Guidelines to Ecology for actions consistent with the
opinion. In all other respects the
Guidelines were found valid.
In
dissent, one Board member found the "guidelines do not implement the ESA,
but rather implement the SMA in a manner consistent with the ESA." This view holds that express authority is
not needed as long as the substance of the Guidelines fall within the scope of
the SMA. This Board member also found
that Ecology did not violate requirements to prepare a SEIS, Implementation
Plan and Cost-Benefit Analysis.
In
dissent, two Board members found that the Guideline's improperly require
preservation and restoration of Properly Functioning Conditions. They determined the Guidelines improperly
shifted the balance of priorities under the SMA from a structure that promotes
a "balancing of interests" to
one that promotes "habitat restoration." These Board members held that the Guidelines effectively
prohibited gravel mining and that they operate to impose an un-funded mandate
on local governments.
NOTE: This article was
written by Eric Z. Lucas. Here is his
biographical information. Eric Z. Lucas
began his service as an Administrative Appeals Judge for the Boards of the
Environmental Hearings Office in February 2002. Prior to his appointment,
Mr. Lucas served for eleven years as the City Attorney for the City of Langley,
Washington. The last two years of his
tenure in Langley he also held the position of City Administrator. Mr. Lucas has been a Judge Pro Tem for Snohomish
County Superior Court since 1999. In
1986, he began his legal career as a criminal division Deputy Prosecuting
Attorney for King County, Washington (1986-1989). Mr. Lucas attended Stanford University as a Creative Writing
major and a member of the Stanford Writer's Workshop. He is a graduate of the University of Washington with a degree in
English Literature. He received his JD
degree from Harvard Law School, Cambridge, Massachusetts in 1986.