|
The following notes summarize some of the more significant matters
heard and decided by the Pollution Control Hearings Board and
Shorelines Hearings Board over the past year since January 2000.
SEPA
The FPAB was asked to address whether a watershed analysis done under
the Forest Practices Act complied with SEPA, specifically whether DNR
had considered future forest practices in reviewing the watershed
analysis and in making the SEPA threshold determination. In this
instance, the FPAB found it acceptable for DNR to assume that all
landowners within the watershed would harvest all available timber
within the watershed, rather than requiring a list of specific future
harvests. The FPAB reasoned that to require the actual list of future
harvests might be too changeable given market conditions, and thus not
as reliable a predictor of environmental effects. Kettle Range
Conservation Group and the Lands Council v. Department of Natural
Resources, FPAB Nos 98-33, 99-18 &00-006 (2000).
Water Rights and Water Quality.
One of the more visible opinions issued by the PCHB in 2000 involved
the proposal to construct the Crown Jewel Gold mine in Okanogan County.
Okanogan Highlands Alliance, et al v. Department of Ecology and Battle
Mountain Gold Co., PCHB Nos. 97-146, 182, 183, 186, & 99-019
(2000).
The Crown Jewel Mine was proposed to be developed near the summit of
Buckhorn Mountain. It would have resulted in the creation of an open
pit mine approximately 116 acres in size and approximately 800 feet
deep, extending 350 feet below the existing water table. During mining,
a series of wells and pumps would keep groundwater and surface water
out of the pit. At the conclusion of mining, the pit would begin to
fill with water and create a lake. Water from one of the creeks would
be pumped into the pit until it was filled. Once filled, the lake would
discharge into one of the creeks to fulfill water rights and as part of
the proposed mitigation.
The company applied for numerous water rights, changes to existing
water rights and reservoir permits. Analysis indicated the proposed
appropriation of water would result in streamflow depletions in several
of the watersheds. Because this might lead to impairment of senior
rights and reduced flows necessary for fish and instream resources, a
mitigation plan was developed which relied on pumping and storing
waters for release to all affected basins. The PCHB found the
mitigation plan failed to account for all streamflow depletion during
several critical stages and contained too much uncertainty to
adequately protect existing rights and instream flows. Additionally,
the PCHB found that Ecology had failed to consider the cumulative
impacts of granting these water rights in light of the concurrently
planned or reasonably foreseeable future actions, such as the ability
of local water supplies to accommodate anticipated increases in
population growth. The PCHB found that the mitigation plan
substantially underestimated the likely streamflow depletions and
required mitigation quantities.
On the issue of water quality, the PCHB found that the modeling to
support the �401 permit was conducted over too short a timeframe and
with an inadequate number of samples. The board was also concerned
about relying on the construction of a water treatment plant with its
requirement for perpetual maintenance and upkeep. Especially troubling
was the failure to address what would happen to water quality during
the construction of the treatment plant.
The PCHB was also concerned about the proposed waste rock facilities.
The PCHB found that Ecology had not obtained sufficient information to
provide reasonable assurance that water quality standards would be
protected from leachate discharging from the waste rock facilities.
Finally, the Board found that the mine would result in direct and
indirect effects on wetlands. The offsite mitigation was deemed to be
insufficient to compensate for the impacts to wetlands. Most of the
mitigation provided for the protection of existing already protected
wetlands.
In summary, the PCHB found that the proposed mine would have
resulted in the increased consumption of water and in a permanent shift
in the hydrogeologic divide between two watershed basins, both of which
had been closed to new appropriations. The pit lake was projected to
violate state water quality standards from metals leached from the
exposed rock walls. The waste rock piles were also predicted to leach
pollutants and not meet state water quality standards. The proposed
mitigation was deemed not legally sufficient to meet the criteria for
approval of the water right applications or provide reasonable
assurance for the �401 Certification. The mitigation and the permanent
engineering solutions were viewed as highly speculative and uncertain.
The PCHB was troubled that the only real assurance provided for
protecting the environment was the bonding that the state might need to
rely on to enforce environmental laws in the future.
As a result, the PCHB reversed the water right reports of examination and vacated the �401 certification.
Abandonment of Water Rights
In PUD No. 1 of Pend Oreille County v. Ecology, 97-177, 98-043 &
044 (2000), the PCHB was faced with determining whether a Public
Utility District (PUD) had abandoned its 1907 water rights and whether
instream flow conditions imposed in its �401 certification were
appropriate.
From 1910 to 1956, the dam and reservoir in question were owned by two
cement companies in Metaline Falls who stored waters for later release
through a bypass wooden flume and canal system to a powerhouse where
power was generated. In 1956, the PUD acquired the facilities which had
ceased power production. In 1958 and 1959, the predecessor to the
Federal Energy Regulatory Commission (FERC) issued a license for the
storage and release of waters in Sullivan Lake and contemplated the
re-establishment of hydroelectric power in the Sullivan Lake Project.
In 1994, the PUD filed an application with FERC to amend its earlier
license. In conjunction with the FERC application, the PUD filed two
applications with the Department of Ecology to change the point of
diversion for two of its water rights. Additionally, they applied for a
water quality certification under �401 of the Clean Water Act. Ecology
denied the change application for one of the water right applications
on the basis that the rights had never been perfected. Ecology denied
the change application on the second water right finding that the water
right had been abandoned. Ecology also imposed instream flow conditions
in the �401 certification.
From 1956 until the present, the PUD had engaged in various
applications and feasibility studies to redevelop the project under the
FERC application. The department of Ecology contended, however, that
the long period of non-use of the water rights established a
presumption of abandonment under the standards set by the state Supreme
court in O.W.L. v. Town of Twisp, 133 Wn.2d 769 (1997). Ecology also
contended that the collapse of the water flume in 1956 and language in
the non-generating license indicating that the Sullivan Lake Project
had been abandoned, were further evidence of abandonment. Ecology
argued that the PUD was simply trying to hold the water rights for
future speculation.
Under Twisp, the two critical elements of abandonment are non-use
coupled with an intent to relinquish rights in water use. The burden of
proof rests with the party asserting abandonment, in this case Ecology.
Where there is evidence of a long period of non-use, the burden may
shift to the water right claimant to justify non-use. The PCHB
concluded that there was questionable evidence to support a rebuttable
assumption of abandonment. Further, if a rebuttable assumption applies,
the PUD had shown that it did not intend to relinquish its 1907 water
rights. The PCHB based its decision on the evidence showing the PUD’s
continued efforts to explore options for changes and new licenses and
the PUD’s payment of their annual power licensing fees. The PCHB
distinguished the facts in this case from those in the Twisp case and
from those in several out-of-state cases denying speculative water use
ventures. The PCHB found that where the PUD was continuously engaged in
some affirmative effort to put the diversionary water right to
beneficial use, it was not speculation. The voluminous business records
presented to the PCHB did not divine an intent to abandon.
On the water quality certification, the PCHB upheld the inflow
flow conditions in the �401 certification as reasonably calculated to
protect the existing fisheries habitat in Sullivan Creek within the
bypass reach.
The PCHB had previously had entered summary judgment in 1998
resolving other issues in this appeal. Both the summary judgment and
the final decision are on appeal to the Supreme Court.
Water Right Relinquishment
In Willows Run Golf Course v. Ecology, PCHB 00-160 (2001), order
granting partial summary judgment, the PCHB was asked to determine
whether the water right relinquishment statute applied to permits and
certificates issued before the enactment of the relinquishment statute
(1967). The appellants contended the statutory language limited
relinquishment to only those water right appropriations which had
received a certificate after the effective date of the statute. Both
parties asserted that the statutory language was unambiguous, but then
gave diametrically opposed interpretations as to its meaning. The PCHB
found strong evidence of a legislative intent to render all water
rights subject to relinquishment provisions. Given the legislative
finding for a strong beneficial use requirement, the PCHB indicated
that the relinquishment statute applies to the exercise or non-exercise
of a water right after the effective date of the act, not to when a
water right certificate was issued.
Collateral Estoppel
The PCHB (and the SHB) is often asked to rule on the preclusive effect
of prior litigation involving a particular proposal. See Weyerhaeuser
and CROWD v Tacoma-Pierce County Health Department, Land Recovery, Inc,
and the Department of Ecology, PCHB No. 99-067 (2000). In this case,
the appellants challenged the Tacoma-Pierce County Health Department’s
modification of a solid waste permit issued to Land Resources, Inc
(LRI). The underlying permit and associated conditional use permit
issues were appealed at various levels to Superior court, state Supreme
Court, US District Court and the Ninth Circuit Court of Appeals. The
complexity of this proposal cannot be easily summarized in a paragraph.
At issue in this appeal was whether the health department had made a
practicable alternatives demonstration on wetland impacts. The original
permit expressly acknowledged a “successful demonstration” on
practicable alternatives. The permit was appealed directly to Superior
Court. While that matter was pending, the Army Corps of Engineers
(Corps) ruled that the alternatives demonstration was not adequate. The
Superior Court nonetheless affirmed the permit and determination made
by the health department. There was no appeal of the Superior Court
judgment.
In a subsequent appeal of the Corps’ ruling, the Ninth Circuit held
that the health department determination on practical alternatives was
controlling and that the Corps was without jurisdiction in the matter.
The permit modification was simultaneously appealed to the PCHB and
Superior Court. In that action the trial court issued a letter ruling
that any challenge to the practical alternatives determination was
barred under the doctrine of collateral estoppel. The PCHB similarly
found that all the elements of collateral estoppel had been met and
dismissed the case.
A dissenting opinion countered that the elements of the collateral
estoppel doctrine were not met in this case because all the parties
anticipated that the Corps would play a role in the “practicable
alternatives” analysis, but was later ruled to be without jurisdiction.
The dissent argued that an appellant can claim injustice under
collateral estoppel and thwart its application. The dissent pointed to
the injustice of losing a right to challenge given the reliance on the
integral role anticipated for the Corps, prior to the Ninth Circuit
ruling. What remained to complete this picture, according to the
dissent, was a demonstration that LRI had rebutted the presumption of
the existence of practicable alternatives, absent Corps involvement.
The summary judgment of the PCHB was not appealed.
Pesticide spraying for aquatic species
Several herbicide and pesticide cases were before the PCHB in 2000 and
early 2001, one relating to spraying glyphosate (aka Rodeo�) to control
the spread of Spartina in the waters of northern Puget Sound and one
relating to spraying Carbaryl on commercial oyster beds in Willapa Bay
to control burrowing shrimp. In both cases, the PCHB granted summary
judgment to the applicators (respondents).
The PCHB has addressed the subject of Spartina control in several
appeals over the past five years. Appellants have generally challenged
the issuance of water quality modification orders or the need for a
shoreline permit for the use of the chemical in the aquatic
environment. In Ortman, et al v. Departments of Agriculture and
Ecology, PCHB 99-115 &116 (2000), the appellants argued that a
NPDES permit was also required. First, the PCHB found that RCW
90.48.445 prohibited the department from requiring a NPDES permit. The
statute strictly limits the conditions that may be imposed on permits
issued for aquatic noxious weed control. Second, the failure to require
or issue a NPDES permit was not a matter within the jurisdiction of the
PCHB. Third, the PCHB found that the application of an herbicide to
control noxious aquatic weeds independent of a commercial or industrial
operation does not constitute the disposal of waste within the meaning
of RCW 90.48.160.
The dissenting opinion found that neither Ecology nor Agriculture had
pointed to any federal or state NPDES exemption for aquatic herbicidal
applications. The dissent also noted concerns about the potential
cumulative environmental impacts from glyphosate, especially given the
concerns noted in the EIS about the long-term impacts. Due to the
legislative changes, the permit at issue in this case decreased the
drying time for application, doubled the allowable wind-speed, and
increased the rate of application significantly above that studied in
the EIS. Because of these changes, uncertainties and the lack of
studies recommended in the EIS, the dissent urged caution and diligence
by the regulatory agency in granting water quality modifications.
Finally, the appellants asserted that the conditions of the permit had
been violated. The PCHB reiterated that it does not have jurisdiction
to consider enforcement matters absent an underlying enforcement action
or order from the Department of Ecology. Although such an order was not
present, the alleged violations were considered insofar as they might
relate to whether there had been a substantial change in the proposal
that would likely have a significant adverse environmental impact. The
PCHB found no evidence that such a change had been made. As a result,
the summary judgment was granted affirming the water quality
modifications and dismissing the appeal. The decision of the board was
not appealed.
In Ad hoc Coalition for Willapa Bay v. Dept. of Ecology and Willapa
Bay- Grays Harbor Oyster Growers Association, PCHB 00-115 (2001), the
PCHB granted summary judgment for the Oyster Growers due primarily to
the failure of the pro se appellants to meet their burden of citing any
statute or regulation being violated or of showing any facts supporting
the alleged violations. Additionally, they failed to provide any
analysis explaining how the facts might support finding a violation of
applicable law. The PCHB noted the pro se status of the appellants, but
declined for a variety of reasons to suspend the requirements they
needed to meet to thwart the granting of summary judgment. The Oyster
Growers were able to show that the spraying was monitored under the
conditions of the order.
Of particular note in this case was the mootness argument. The Oyster
Growers alleged the appeal should have been dismissed as all the
spraying had already taken place and the permits had expired. The PCHB
rejected this request, recognizing the public interest exception to the
mootness doctrine. Under this exception, a matter is not moot where the
issue is of a public interest, likely to recur, and an authoritative
determination would provide future guidance to public officers.
Carbaryl has been employed for many years in Willapa Bay to control
burrowing shrimp. The Oyster Growers anticipate future orders
authorizing the use of Carbaryl. If the PCHB were to apply the mootness
doctrine, there would essentially be no effective right to appeal those
future orders. On this matter, the PCHB did not grant summary judgment.
Pro se appellants
Several cases before the boards this year have been aimed at the
responsibilities of appellants, especially pro se appellants. WAC
371-08-385 and 461-08-405 allow the PCHB and SHB respectively to waive
any of their procedural rules, other than those relating to
jurisdiction, for any party not represented by legal counsel. As noted
above, the appellants in Ad hoc Coalition for Willapa Bay had practiced
before the board and were assumed to know how to properly present
issues, facts, and analysis. The PCHB declined to waive the procedural
requirements. In Ziak v. Pacific County, SHB 00-024 (2001) the pro se
appellant failed to respond to discovery and generally ignored
deadlines set in the case. The SHB indicated that the appellant took on
a public as well as private responsibility to participate competently
and fully in the process. Failing to do so resulted in there being no
material facts at issue. The case was therefore dismissed. And finally,
in Miller et al v. Coutts and the City of Bremerton, SHB 00-030 (2001),
the pro se appellants brought a motion for summary judgment. In the
order denying the motion, the SHB urged the pro se appellants to work
with an assigned Administrative Judge to better understand the SHB
procedures for presenting their case at the hearing. For a variety of
reasons, most notably the constraints of administrative practice, the
pro se appellants decided to drop their case.
Docks
Numerous dock cases were decided by the SHB addressing navigability,
appropriate length, availability of alternative moorage, mandatory
joint usage agreements, protecting salmon and cumulative impacts. In
Holley v. San Juan County, SHB 00-002 (2000), the SHB upheld the denial
of a permit to build a recreational dock on the basis that alternative
moorage, at a marina in Friday Harbor, was adequate and feasible for
the appellant, even with a reasonable waiting period. For the SHB, cost
for moorage was not controlling. The issue was availability of moorage.
In Close v. San Juan County, SHB 99-021, the SHB upheld the denial of a
new dock also on the basis that adequate moorage was less than a mile
away, and they had a mooring ball and moderately reasonable beach
access for launching personal watercraft. The SHB felt the dock would
also be a visual and physical barrier to the public attempting to
access the shoreline and to kayakers along the shore.
In Bishop v. San Juan County, SHB 99-034 (2000), the appellants sought
review of conditions imposed by San Juan County limiting the length of
their dock to the +2.5 tide elevation and requiring the dock to be a
multiple use facility. Because the island does not have ferry service,
the SHB determined that a dock was necessary for year round access to
the residence. The SHB found this dock did not intrude significantly
into the shoreline environment, had a low profile and was generally
compatible with other developments in the bay. There was significant
concern about cumulative impacts. The SHB presumed that in the future
it was very likely the owners of the remaining lots in the subdivision
along this shoreline would want longer docks. The impact would result
in the very “porcupine effect” that the County’s regulations sought to
avoid. Multiple-use docks were therefore critical to limiting the
proliferation of individual docks. The SHB determined that the dock
could not be approved unless it was a joint-use facility, including a
recorded deed restriction allowing for joint use by specific lots in
the subdivision.
In Viafore v. Mason County, SHB 99-033 (2000), a neighbor challenged a
shoreline permit for the construction of a 100-foot pier and floating
dock in an area with virtually no other docks. The appellant contended
the dock would have an adverse impact on salmon migration. In reviewing
the literature on the effects of shading on salmon migration, the SHB
concluded that the proposed dock would probably have no adverse impact
on salmon migration. It did note the lack of definitive scientific
knowledge on the subject, especially in the context of cumulative
effects. The SHB also considered the proposal’s relation to potential
future development of similar docks along this stretch of Puget Sound.
The SHB found the dock would impact the views on an extensive shoreline
with almost no dock development. The SHB was concerned about the
precedent that would be set by authorizing this “first” dock and thus
denied the permit.
Finally, the SHB took up the issue of protecting navigability in the
cases of Harborview Marina v. Gig Harbor, SHB 99-013 (2000) and Mukai
&. Parkshore Marina v. Seattle & Spinnaker Bay Marina, SHB
00-029 & 032 (2001). Both cases involved the maneuverability of
boats between piers. In both cases, the SHB looked at balancing
competing interests and determined that navigability, especially given
NW winds and weather, had not been adequately protected. In Mukai, the
SHB declined to accept the US Army Corps of Engineers’ determination as
to what would adequately protect the public right of navigation. In
both cases, the permits were remanded to the local government to better
address navigability and maneuverability.
Non-conforming uses
The SHB had several cases involving non-conforming structures built or
uses authorized before the adoption of the Shoreline Management act. In
Ecology v. Lewis County and Cowlitz Timber Trails Association, SHB
00-027 (2001), the SHB was asked to address accessory buildings at a
camping development along the Cowlitz River. An earlier Compromise and
Settlement Agreement had determined that some of the structures and
uses would be considered non-conforming. The issue before the SHB was
whether these additional structures (gazebos, RV covers, and decks)
were also “non-conforming” and what standards governed their
authorization. The SHB determined that the proposed structures were an
inappropriate expansion of a non-conforming use. Specifically, the
proposed structures were inconsistent with the Lewis County Plan’s
directive for a conservancy environment, notably allowing more than
diffuse, low intensity, or non-permanent recreational activity.
In Fox v. Ecology, SHB 00-025, the SHB allowed a conditional use permit
to enclose an overwater deck on a non-conforming small cabin. The SHB
used a balancing approach to reach its conclusion, noting specifically
that the enclosure would not increase the non-conformity. The balance
looked at neighboring development, most of which were much further
waterward and much larger. Also, there was no evidence of any
environmental harm, and in reality, given the need to connect the cabin
to septic, an environmental benefit to allow the project to proceed.
The permit was conditioned on the applicants receiving an approved
septic system. A dissenting opinion contended any expansion of an
overwater residential development was specifically prohibited by the
County’s master program, and it was inappropriate to rely on other
non-conforming structures to justify the granting of a variance. |